RE: SITE ANNOUNCEMENT - jft310 - 07-02-2015

'ArtM72' pid='60114' dateline='<a href="tel:1435837 Wrote:Bummer....again. Reads like a six month setback. Anybody see a silver lining on this cloud? And the name? That selection is inspired.

The silver lining is the gas in place is substantially larger than prior estimates. Thus a push. Which means we get paid a ton more more . If 11.8 T's that's $3.5 Billion in total Total payments to Interoil ,if 9.9 T's the payments are $2.8 Billion . Or 1.9 T's yields Interoil an additional 700 million . Plus extra LNG revenue over 20 years plus . Worth proving out more .

Getting the size right saves millions .

Not sure we are losing much time in reality .




RE: SITE ANNOUNCEMENT - ArtM72 - 07-02-2015

Let's face it (Again). With the same rig being used for antelope five, four and six with the possibility of an antelope seven A mid 2016 certification payment seems most likely. Plant site selection. Big deal. Been here two times before.


RE: SITE ANNOUNCEMENT - ArtM72 - 07-02-2015

'jft310' pid='60123' dateline='<a href="tel:1435839 Wrote:

'ArtM72' pid='60114' dateline='<a href="tel:1435837 Wrote:Bummer....again. Reads like a six month setback. Anybody see a silver lining on this cloud? And the name? That selection is inspired.

The silver lining is the gas in place is substantially larger than prior estimates. Thus a push. Which means we get paid a ton more more . If 11.8 T's that's $3.5 Billion in total Total payments to Interoil ,if 9.9 T's the payments are $2.8 Billion . Or 1.9 T's yields Interoil an additional 700 million . Plus extra LNG revenue over 20 years plus . Worth proving out more .

Getting the size right saves millions .

Not sure we are losing much time in reality .

Nonsense.




RE: SITE ANNOUNCEMENT - AU74 - 07-02-2015

I think no news is good news on size and capacity. If two trains is a given, then the fact they didn't say two train would suggest that more than two are being considered. Same could be said for the size of each train. Assume 3.5 each, if that's the norm, and the fact they don't specify beyond that only leaves upside.


RE: SITE ANNOUNCEMENT - MartiniStocks9756 - 07-02-2015

They could have said minimum two trains. And that would have been a winning Presser.


RE: SITE ANNOUNCEMENT - ArtM72 - 07-02-2015

MartiniStocks9756 dateline='<a href="tel:1435840730">1435840730</a>' Wrote: They could have said minimum two trains. And that would have been a winning Presser.

The Presser could also have been titled "9 month delay announced for new Papua LNG".

How often was the project timeline used in the past year with concept selection shown at the end of 2Q15?




RE: SITE ANNOUNCEMENT - MartiniStocks9756 - 07-02-2015

It depends on your definition of concept. They gave their concept a new name and where it is to be located and how they are going to get the gas to the facility. I agree we all were expecting more. Maybe we should dissect it more from a business point of view instead of a shareholders point of view. It certainly makes sense they cannot completely estimate size until certification is complete. Maybe that should have been discussed at AGM and not assume that we all are on the same page. It all begins at Final Investment Decision and we just have to be patient which is difficult. Meanwhile, the stock went backwards because why? Maybe it ran up to quick and needed to consolidate before the next leg up.


RE: SITE ANNOUNCEMENT - Li'loilady - 07-02-2015

'ArtM72' pid='60131' dateline='<a href="tel:1435841 Wrote:

'MartiniStocks9756' pid='60128' dateline='<a href="tel:1435840 Wrote:They could have said minimum two trains. And that would have been a winning Presser.

The Presser could also have been titled "9 month delay announced for new Papua LNG".

How often was the project timeline used in the past year with concept selection shown at the end of 2Q15?

This was our mid-year/end of 2Q15 Concept Selection.

Per Stavros, a following Basis of Design, which Hession referred to in the PR, is expected to give us size of trains etc.  I agree with Martini that including the obvious, "minimum 2 trains," would have made for a cleaner PR but, I don't  see anything here that implies delay.

Certification will likely be delayed, hopefully by only 1Q, due to the Western rig problem, higher pressures, a 3rd (or 4th) appraisal well and whatever other lightning might strike between now and then.




RE: SITE ANNOUNCEMENT - Palm - 07-02-2015

'ArtM72' pid='60121' dateline='<a href="tel:1435838 Wrote:

'Tree' pid='60117' dateline='<a href="tel:1435837 Wrote:Site selection = Commitment to develop (This is a big deal) Chosen site = Cooperation by XOM (This is a big deal) Much pre-planning completed, need re-cert, do simple math and declare how many trains. Did anyone really expect #trains announced prior to re-cert??

Yes. I sure did. We all did. That is what we were told.  Plant expansion upon finding more gas is the industry norm.

We know the # of trains will be at least 2; in fact they wouldn't start with less. There was discussion the other day on this. Industry standard is at least 2 to start and highly unlikely they will start with more. We have been saying for years to use PNG LNG as a "pattern" for a project, but now that isn't good enough anymore?  We should have learned by now that we will follow industry standards.




RE: SITE ANNOUNCEMENT - AU74 - 07-02-2015

I was just looking at the IOC milestone chart from January to compare to today's news. I'll be ignoring the Eeyore comments on here that are calling this a six month slip, then a nine month slip (who knows what the next doom and gloom accusation will be). Looks more like the project is on schedule to me.