OSH drilling update - Li'loilady - 10-07-2016

http://www.oilsearch.com/Media/docs/161006%20Drilling%20Report%20for%20September%202016-a14e5229-491d-43f8-8882-622fe630dbb7-0.pdf
Antelope 7 Gas appraisal
PRL 15, Gulf Province, PNG 1.4km WSW of Antelope-5
Rig:  HA 115
Purpose: To test for reservoir presence and definition on the western flank of the field.
During the month, the mobilisation of Rig HA115 from Herd Base to the Antelope 7 drill site commenced. At the end of September, the rig move was 92% complete and rig-up was 37% complete.



RE: OSH drilling update - Stavros - 10-07-2016

Ha!

No news from the Operator, TOTAL

No news from our employee, mr hession

What a bunch of Mother Fuddruckers
http://www.fuddruckers.com/


RE: OSH drilling update - Kaliboo - 10-08-2016

'Li'loilady' pid='76725' dateline='<a href="tel:147 Wrote:

Antelope 7 Gas appraisal
PRL 15, Gulf Province, PNG 1.4km WSW of Antelope-5
Rig:  HA 115
Purpose: To test for reservoir presence and definition on the western flank of the field.
During the month, the mobilisation of Rig HA115 from Herd Base to the Antelope 7 drill site commenced. At the end of September, the rig move was 92% complete and rig-up was 37% complete.

Be real guys.  Hession is too busy counting our millions that he has/is stealing to worry about updates on A7.  I'm sure there is a collective agreement to delay spud until the deal is fully executed and IOC is history.  At least OSH is still reporting.  Thanks Olady for posting this.




RE: OSH drilling update - 2126 - 10-08-2016

Do we know if the current location [1.4 km WSW of A5] is the new location that Phil [and Pet] indicated was a better location than the original one Hession selected?




RE: OSH drilling update - johnwgrant - 10-08-2016

Based on "rig-up" 37% complete, what are the experts predicting regarding spud date? IE, how long does it take to rig-up this type of drilling rig ?!?!


RE: OSH drilling update - johnwgrant - 10-08-2016

And don't answer "how long is a string?!?!" Wink


RE: OSH drilling update - ArtM72 - 10-09-2016

'johnwgrant' pid='76739' datel Wrote:And don't answer "how long is a string?!?!" Wink

Sweet response.