Project partner Oil Search said the funds were sourced from co-venturer and commercial bank lenders and takes the total project financing facility to $15.5 billion.
“We are pleased that the supplemental project financing has been completed and all funding is now in place to complete the Project on time and within the revised budget,” Oil Search managing director Peter Botten said.
The funds raised will be used to finance the debt component of the project cost increase which was announced in November last year.
The project was hit with a $3.3 billion capital cost increase which was blamed mainly on foreign exchange, while delays from stoppages due to community disruptions and land access led to increased construction and drilling costs. Weather related challenges and logistics costs also added to the overall cost of the project.
The PNG LNG project involves the construction of a two-train processing plant with a capacity of 6.9 milllion tonnes per annum.
Operator ExxonMobil holds a 33.2% stake in the project and is partnered by Oil Search on 29%, PNG government company Independent Public Business Corporation on 16.6%, Santos on 13.5%, Nippon Oil on 4.7%, PNG’s Mineral Resources Development Company on 2.8% and PNG national oil company Petromin on 0.2%.
First gas from the $19 billion project is scheduled to start flowing in the second half of next year.