What are we doing at Wahoo? - petrengr1 - 05-26-2015
What might be going on at Wahoo? Here is what we have been told:
From MD&A May 12, 2015
1. “PPL 474 - Wahoo drilling program - Wahoo-1 exploration well is about 170 kilometers southeast of our Elk and Antelope gas fields. On July 14, 2014, we announced that we had suspended drilling the Wahoo-1 well in PPL 474 after intersecting gas and higher-than expected pressures. The DPE approved this suspension to enable us to re-evaluate the drilling plan. - The mobilization of crew to site is currently ongoing, and we intend to resume drilling in the second quarter of 2015.”
2. “ Increase in cash outflows on exploration and development expenditures was mainly due to the site preparation and pre-spud costs for the Triceratops-3, Wahoo-1 Side Track and Antelope 6 well, and drilling costs incurred for the Antelope-4 and Antelope-5 wells.”
3. “Costs for site preparation and pre-spud work of the Wahoo side track well.”
From Presentation of May 12, 2015
1. “Wahoo and Triceratops-3 to drill mid-year”
Under Wahoo:
1. “Rig preparing side-track with new well design and larger blow-out preventer”
2. “Re-entering expected mid-year”
Comments:
You must understand that the following is speculation if it is not included in the above statements from the company.
So we know that the crew was being mobilized on May 12th (or earlier). That should not take more than a day or two since the Wahoo site is accessible by road. What is the crew doing? They must not just be idle.
1. They probably have dual down hole deployment valves in place in the 7” and 9 5/8” casing strings. The valves in the 7” are probably now closed..
2. The crew could be changing out the blow out preventer (BOP). They say they will be installing a “larger blow-out preventer”. I take that to mean they will have one or more additional sets of rams that are capable of closing off the annular part of the hole and a higher pressure rating than the old BOP. I had thought they might bring in a BOP that was capable of running a larger size casing but that would only be needed if they were starting a new well from the surface. Since they are side tracking the existing well that will not be needed on this well. It is still possible that they have that capability for use on future Wahoo wells.
3. Next they will need to circulate the old mud out of the hole, clean out the open hole to TD and plug the open hole with cement. We do not want to leave a path (open hole) for the formation to flow through as we drill the side track hole nearby.
4. We will then need to plug the bottom of the 7” liner.
5. Next we will need to recover the “tie-back” part of the 7” liner and plug the top of the remaining 7” liner.
6. I do not know if they intend to side track out of the 9 5/8” liner or the 13 3/8” casing. If they intend to side track from the 13 3/8’ casing they will need to recover the tie-back or upper part of the 9 5/8” liner and plug the top of the remaining 9 5/8” liner with cement.
7. After pulling the liners they will mill out about 40 feet of the casing where they intend to side track. That will be either the 9 5/8” or the 13 3/8”. In order to have more casing size options I think they will probably come all the way back to the 13 3/8” casing.
8 After milling out the window in the casing they will set a cement plug and probably a whipstock to allow the drill string to exit the old well through the 40 foot window. Then we will be off to drilling the new sidetrack well.
Since they have mobilized the crew I think they will announce at the AGM, or before, that work has commenced. They have said they would be commencing by mid-year but I think they will beat that target.
They have said “side track” and “re-enter” so it is clear that they will not be starting a new well from the surface. They have used the word "spud" which usually means to start a new well from the surface but in this case that is not what they mean.
RE: What are we doing at Wahoo? - admin - 05-26-2015
Thanks, Pet, finally things are moving on. It will be an interesting second half of the year.
RE: What are we doing at Wahoo? - Thylacine-2 - 05-27-2015
'petrengr1' pid='58404' datel Wrote:
What might be going on at Wahoo? Here is what we have been told:
From MD&A May 12, 2015
1. “PPL 474 - Wahoo drilling program - Wahoo-1 exploration well is about 170 kilometers southeast of our Elk and Antelope gas fields. On July 14, 2014, we announced that we had suspended drilling the Wahoo-1 well in PPL 474 after intersecting gas and higher-than expected pressures. The DPE approved this suspension to enable us to re-evaluate the drilling plan. - The mobilization of crew to site is currently ongoing, and we intend to resume drilling in the second quarter of 2015.”
2. “ Increase in cash outflows on exploration and development expenditures was mainly due to the site preparation and pre-spud costs for the Triceratops-3, Wahoo-1 Side Track and Antelope 6 well, and drilling costs incurred for the Antelope-4 and Antelope-5 wells.”
3. “Costs for site preparation and pre-spud work of the Wahoo side track well.”
From Presentation of May 12, 2015
1. “Wahoo and Triceratops-3 to drill mid-year”
Under Wahoo:
1. “Rig preparing side-track with new well design and larger blow-out preventer”
2. “Re-entering expected mid-year”
Comments:
You must understand that the following is speculation if it is not included in the above statements from the company.
So we know that the crew was being mobilized on May 12th (or earlier). That should not take more than a day or two since the Wahoo site is accessible by road. What is the crew doing? They must not just be idle.
1. They probably have dual down hole deployment valves in place in the 7” and 9 5/8” casing strings. The valves in the 7” are probably now closed..
2. The crew could be changing out the blow out preventer (BOP). They say they will be installing a “larger blow-out preventer”. I take that to mean they will have one or more additional sets of rams that are capable of closing off the annular part of the hole and a higher pressure rating than the old BOP. I had thought they might bring in a BOP that was capable of running a larger size casing but that would only be needed if they were starting a new well from the surface. Since they are side tracking the existing well that will not be needed on this well. It is still possible that they have that capability for use on future Wahoo wells.
3. Next they will need to circulate the old mud out of the hole, clean out the open hole to TD and plug the open hole with cement. We do not want to leave a path (open hole) for the formation to flow through as we drill the side track hole nearby.
4. We will then need to plug the bottom of the 7” liner.
5. Next we will need to recover the “tie-back” part of the 7” liner and plug the top of the remaining 7” liner.
6. I do not know if they intend to side track out of the 9 5/8” liner or the 13 3/8” casing. If they intend to side track from the 13 3/8’ casing they will need to recover the tie-back or upper part of the 9 5/8” liner and plug the top of the remaining 9 5/8” liner with cement.
7. After pulling the liners they will mill out about 40 feet of the casing where they intend to side track. That will be either the 9 5/8” or the 13 3/8”. In order to have more casing size options I think they will probably come all the way back to the 13 3/8” casing.
8 After milling out the window in the casing they will set a cement plug and probably a whipstock to allow the drill string to exit the old well through the 40 foot window. Then we will be off to drilling the new sidetrack well.
Since they have mobilized the crew I think they will announce at the AGM, or before, that work has commenced. They have said they would be commencing by mid-year but I think they will beat that target.
They have said “side track” and “re-enter” so it is clear that they will not be starting a new well from the surface. They have used the word "spud" which usually means to start a new well from the surface but in this case that is not what they mean.
Pet, would you share your thoughts about why the decision was made to go with a side track?
RE: What are we doing at Wahoo? - sageo - 05-27-2015
Pet - A 'bundle' of thanks for your post on our "proceedings" at Wahoo . Be well and kindly continue your unselfish sharing of your vast knowledge concerning our "predicaments" that we quite often find ourselves encountering . Please keep up the great work ! ....(and hopefully help our "leaders" with their problem solving) . To quote "Red S." again, ' God Bless' .
RE: What are we doing at Wahoo? - petrengr1 - 05-27-2015
Thy- That is a tough one for me to analyze. The answer is of course that they must believe they can get the well drilled and obtain the information they want cheaper by side tracking than they can by starting over at the surface.
I would have probably guessed that they would start over from the surface so they would have the option to completely revise the casing program. We have some new people since they drilled Wahoo-1. Mr. Tom Junker has joined IOC as Vice President Drilling. He has 34 years of drilling and completions experience. He probably had some influence in this decision. They apparently decided that some errors were made on the first attempt that they can avoid with the information they now have about the formation, the pressure and the depth of the permeable zone that is flowing gas into the well bore.
I believe they will use an improved mud system that will allow them to drill the reactive shale more efficiently. Probably a kcl-polymer-glycol mud system.
They had previously been setting the 9 5/8” casing at the top of the pay zone. On the first attempt at Wahoo they apparently set all of their casing strings, including the 7”, before reaching the top of the pay zone. So I think they would like to at least have the option of setting the 7” casing at the top of the zone. If they do as I suggested they might and come back up all the way to the 13 3/8” casing to side track that will leave them with the 9 5/8” and 7” casing sizes to use after sidetracking. They may have to set the 9 5/8” casing above the permeable gas zone that is above the main pay zone and set the 7” casing at the top of the main pay zone. That would force them to drill a smaller hole than they would like but it would be similar to what was done on the horizontal hole at Antelope-2 where they ran a 5” liner through the 7” casing. That is a tighter fit than most operators are willing to try but they could also use a 4 ½” liner across the pay zone if they wanted to.
So to answer your question as to why they choose side tracking over a new well:
1. They think it will cost less.
2. They will use different and improved mud system.
3. Using the new information they have they will redesign the casing program (setting depth).
4. They have hired some new/additional people and probably consulted with some outside experts.
Now we will have to see how close this fits with what they actually do.
RE: What are we doing at Wahoo? - Thylacine-2 - 05-27-2015
Thanks a lot, Pet. I appreciate your explanation.
RE: What are we doing at Wahoo? - petrengr1 - 05-27-2015
Wahoo-1 was spud on March 10, 2014. I wrote the following post 6 days before the well was spud. IOC has said the reservoir is deeper than they had expected so you can ignore all of the depth numbers that I give because they all came from the IOC map. Since the depth numbers are off the pressure numbers are also off. In fact they have said the pressure they saw was nearly one and a half times what we have at Antelope.
But I find it interesting to compare what I said here before the well was spud to what actually happened when the well was drilled. I will highlight the interesting point in yellow. I believe they found the clastic zone above the limestone reservoir and they found it to be highly overpressured. They just didn't know what depth to expect to find it. Have a good evening/day.
03-04-2014
Wahoo
Let’s have a closer look at Wahoo-1. I suggest that you open
http://tinyurl.com/m32z6ho
and go to slide 19. Magnify the map on the right side so you can see it clearly. Now what have they told us they think is here?
You will see a white and black dotted line at the -1,650 meter contour line. I believe that defines the maximum or potential size of the prospective trap or the lower limit of the reservoir because there is a spill point toward the east near the southern end of the structure. If you look at the location of Wahoo-1 you will see that the well is located on the -900 meter contour line. So if the structure is filled with gas to the spill point we will have a gas column thickness at Wahoo-1 of 750 meters (1,650 -900) or 2,461 feet. You will note on the map that the highest part of the structure is shown to be about -650 meters sub sea or about 250 meters (820 feet) higher than Wahoo-1 so the gas column height for the field might be (2,461 + 820) about 3281 feet (1,000 meters) if the structure is full of gas to the spill point. These numbers apply to the Northern part of the structure. The Southern part of the structure (formerly known as Mako) has four different high spots indicated with a top at around -800 meters sub sea. So the Southern part of the structure (Mako) would have a maximum possible gas column height of about 3,100 feet
We have not yet been given the surface elevation of Wahoo-1 but since it is near the coast let’s assume the elevation is 100 feet above sea level. So we might expect the top of the carbonate zone at Whaoo-1 to be at 3,053 feet (900 meters + 100 ft). Then the aquifer depth or gas water contact might be expected to be at 5,514 feet drill depth if the carbonate zone is more than 2,461 feet thick. All of this assumes the structure is full of gas to the spill point. That is the most optimistic possibility so it might be less than that.
If we find a normally pressured aquifer at a depth of -1,650 meters (5,414 feet) sub sea or 5,514 feet drill depth then the reservoir pressure at the gas/water contact will be 2,388 psi. Most of this pressure will be reflected to the top of the reservoir with the pressure only being reduced by the weight of the gas. If we use a gas gradient of 0.04 psi/ft over the 2,461 foot gas column height (2,461 x 0.04) we will see that the pressure at the top of the reservoir at Wahoo-1 would be 98 psi lower than the pressure at the gas/water contact or about 2,290 psi. If this pressure occurs at the drill depth of 3,053 feet the pressure gradient will be 0.75 psi/ft and will require a mud weight of 14.4 lb/gal to balance or a bit more for safe control.
There is some evidence in the area that the aquifer may be over pressured or that we may have some over pressured zones before reaching the carbonate. Tovala-1 and 1A found high pressure gas and water in the late to mid-Miocene zones above the carbonate. These over pressured clastic zones flowed 1.5 - 2 MMCFD with salt water. If you look at the seismic section to the left of the Wahoo map you will see a yellow line above the top of the carbonate. Could this be an over pressured clastic zone? If so it might require even more mud weight to control than the reef. Do we have the possibility of finding two different reservoirs? One a clastic zone and the other a carbonate reef? What will the reservoirs contain- gas, oil or water?
I hope you found that exercise of some interest.
Now one last point of interest. Look at http://tinyurl.com/mgeqkj7 page 30. The lines you see south of the Popo wells are the seismic lines for Wahoo/Mako. I call your attention to the symbols for all of the wells around Wahoo. Note that the green color in the symbol indicated that these wells had oil shows while drilling and the red star means they encountered gas shows or gas flows.
Most of the closest wells : Tovala, Popo, Iokea, Apinaipi all had oil shows. Those further to the south: Oiapu and Black Bass had both oil and gas shows. By the way Black Bass also encountered an over pressured zone that required a mud weight of more than 14 #/gal to control.
RE: What are we doing at Wahoo? - Thylacine-2 - 05-27-2015
Is a seal (more of the shale) to be expected between the clastic zone at Wahoo and the carbonate? As I recall there was no mention of water from the clastic zone.
RE: What are we doing at Wahoo? - petrengr1 - 05-28-2015
'Thylacine-2' pid='58429' datel Wrote:Is a seal (more of the shale) to be expected between the clastic zone at Wahoo and the carbonate? As I recall there was no mention of water from the clastic zone.
Thy- I expect the shale below the sandstone to be very similar to the shale above the sandstone. Since this sandstone is the highest part of the structure I would not expect it to contain any water. If you look at the seismic section at http://tinyurl.com/m32z6ho page 19 (magnify it so you can see it clearly) you will see that the sandstone approaches or contacts the top of the limestone to the south (right side of the chart) so the sandstone may be in communication with the limestone and reflect the same pressure and content. So we may be seeing the actual reservoir pressure in the sandstone but at a higher elevation. If that is the case the pressure would take more mud weight or be somewhat harder to control. The good news is we probably do not have to worry about losing circulation until we drill into the limestone and find a fractured or very high permeability zone. So they can probably drill through the sandstone and set casing at the top of the limestone if they can keep the hole full of mud of the right weight.
It would be interesting to cleanout the existing open hole below the present 7” casing using an improved mud system, drill through the sandstone, log and cement in place a small diameter liner (4 ½” or even 2 7/8&rdquo and perforate and test the sandstone. They could confirm the content, flow rate and pressure from the sandstone. The open hole would then be properly plugged off before proceeding with the sidetrack and we would have some better information. They could even get some of the information using Schlumberger’s wire line test tool before plugging the present open hole. I don’t expect them to do any of this but instead I expect them to proceed directly with preparations for the sidetrack.
RE: What are we doing at Wahoo? - Thylacine-2 - 05-28-2015
Yes, I see where the sandstone may contact the carbonate at a lower elevation. Given the liquids rich content of the gas from the sandstone, there are interesting possibilities if the sandstone is indeed in communication with the carbonate and reflects the same pressure and content. Didn't the liquids from the sandstone zone at Wahoo indicate the possibility of (dare I say it?) oil?
|