Total selects Elk-Antelope plan - Tree - 06-30-2015

Total has selected its preferred development concept for the Elk-Antelope liquefied natural gas project in Papua New Guinea including the crucial issue of where to locate the LNG plant.

Total has selected its preferred development concept for the Elk-Antelope liquefied natural gas project in Papua New Guinea including the crucial issue of where to locate the LNG plant.

Well-placed sources said an official announcement is planned Wednesday where all details will be revealed.

Sources indicated the LNG plant will be located at Caution Bay near the capital city of Port Moresby.

This is the same location as the ExxonMobil-operated PNG LNG facility.

On the one hand, Caution Bay is the obvious choice, but on the other hand there was political pressure in PNG for the LNG plant to be located in Gulf Province which hosts the Elk-Antelope fields, said sources.

The concept selection will be followed by detailed design work and front-end engineering, with a final investment decision targeted in 2017.

Other details that are expected to be publicised on Wednesday include the number of LNG trains, location of the central processing facility, the gas export scheme and acid gas treatment.

Joint venture partner InterOil said earlier this month the project’s estimated capital expenditure would be about 13% less than the PNG LNG project, which cost US$19 billion.

The forecast construction cost would be about US$2050 per tonne of LNG.

A 90-kilometre onshore pipeline would connect the Elk-Antelope fields with the coast, and a 340-kilometre subsea pipeline would carry gas to Caution Bay.

The Elk-Antelope project is located in Block PRL15. It is operated by Total with a 40.1% interest, InterOil on 36.5%, Oil Search 22.8% and minority interests 0.5%.




RE: Total selects Elk-Antelope plan - my2cows - 06-30-2015

Thanks Tree. I really hope the Gulf province is on board for the plant being in PM. The gulf governor has already issued a warning about this.


RE: Total selects Elk-Antelope plan - Palm - 06-30-2015

Thanks skidaddy! So as expected they locate it right by PNG LNG. Strategically the best spot as now they will be able to feed any of their gas to this location unless PNG LNG wants to bid very high for anything found at Wahoo etc.

The government will now deal with Gulf with assist from Total/IOC/OSH. They will likely throw some nice development with things like CSPs etc. People will scream for a bit but it will get handled.


RE: Total selects Elk-Antelope plan - Putncalls - 06-30-2015

Thanks Tree! I would venture that a one train project would cost a LOT more that 2K$/MTPA given the cost of the IOC gas, the Antelope development and a 300 mile pipeline. It can't be 1.5 trains either. I'll stick my neck out and say that the project consists of 2 trains or more.


RE: Total selects Elk-Antelope plan - Tree - 06-30-2015

You mean the former Gulf Governor. There are plenty of works, facilities and development in Gulf Province to keep them happy. What we do know is XOM Board is 'on board' with the adjacency of the TOT plant. This allows for those 'synergies' and infrastructure sharing Hession has mentioned and XOM didn't sign off just because they like IOC. Now there will be too pipelines to Caution Bay. XOM's which is not at capacity and TOT's which size is TBD. Rex has security.


RE: Total selects Elk-Antelope plan - Palm - 06-30-2015

Puts, no plant gets started with less than two because of economics. If all they had was enough for one train initially, it would go to PNG LNG. We will likely have two large trains at start up.


RE: Total selects Elk-Antelope plan - Putncalls - 06-30-2015

Say that again! LARGE Trains! Two LARGE Trains. Two LARGE liquid producing trains.


RE: Total selects Elk-Antelope plan - Palm - 06-30-2015

Almost sounds foul Puts


RE: Total selects Elk-Antelope plan - my2cows - 06-30-2015

'Tree' pid='60027' datel Wrote:You mean the former Gulf Governor. There are plenty of works, facilities and development in Gulf Province to keep them happy. What we do know is XOM Board is 'on board' with the adjacency of the TOT plant. This allows for those 'synergies' and infrastructure sharing Hession has mentioned and XOM didn't sign off just because they like IOC. Now there will be too pipelines to Caution Bay. XOM's which is not at capacity and TOT's which size is TBD. Rex has security.

I mean this warning. I don't know when this video was created but it circulated on twitter last month. https://www.youtube.com/watch?v=vhnC5W5WHKI

I'm sure Total has the pull, but if the Gulf people are not on-board, we could get some ugly headlines to go along with the concept selection if it truely is in PM.




RE: Total selects Elk-Antelope plan - jft310 - 06-30-2015

If those cost estimates are correct it appears we are 2 trains at 3.5 mtpa. Arun built expandable trains from 3.5 to 4.5 mtpa no idea if that's on the table here.
Stavros listed some synergies in the past between the 2 projects . Share storage tanks etc . He might add a few possibilities .