Comments on the latest Press Release - Printable Version +- ShareholdersUnite Forums (http://shareholdersunite.com/mybb) +-- Forum: Companies (http://shareholdersunite.com/mybb/forumdisplay.php?fid=1) +--- Forum: InterOil Forum (http://shareholdersunite.com/mybb/forumdisplay.php?fid=4) +--- Thread: Comments on the latest Press Release (/showthread.php?tid=9625) |
Comments on the latest Press Release - petrengr1 - 01-23-2016
A few comments on IOC’s latest Press Release http://tinyurl.com/h5mfapn :
1. “the second planned extended well test has commenced at Antelope-5.” Comment: The first test was a four rate flow test with rates between 30 MMCFD and 60 MMCFD over a three day period. They produced a total of 152.9 MMCF. They had a pressure drawdown of ~2 psi and I believe the pressure built back almost to the original reservoir pressure more or less instantly upon the well being shut-in. The stabilized reservoir pressure at Antelope-5 showed a decrease in reservoir pressure of 0.061 psi. This pressure reading came from one down hole pressure recorder. It was the deepest of five pressure recorders and it was set at 1,644.6 meters below the rotary table. I think we have never been told the size of the casing or the depth it was set but it was set at or near the top of the reservoir which was reported to be at 1,680 meters below the rotary table. So this gauge was set just inside the casing above the open hole and no doubt just below the packer on the bottom of the tubing. I can visualize that at flow rates of 50 - 60 MMCFD the pressure recorders might be “knocked around” a good bit during the flow period due to turbulence. I do not know why they only reported the pressure from the lower gauge at Antelope-5 and had nothing to say about the other four gauges. Could it be that they were damaged or quit working?? Now they say: “In order to improve the certainty of the minimum connected volume, we have added additional pressure gauges”. Wow! How much redundancy is required? They were already using five pressure recorders. How many are they using this time??? They plan to produce the well this time ~14 days at a rate of ~50 MMCFD. They say they expect to produce approximately 5 times as much gas this time as they did on the first test which would be about 765 MMCF. If we have no water drive the reservoir pressure should drop 5 times as much as the first test. The loss in reservoir pressure at Antelope-1 was measured at 0.080 psi based on the average of 5 down hole pressure recorders. All five gauges apparently worked at Antelope-1 where there was no turbulence because the well was shut-in. So the average pressure drop between the two wells was ~0.07 psi. We are probably looking for a pressure drop of about 0.35 psi on this new test. 2. “Antelope-6 appraisal well, located 2km eastsouth-east to the Antelope-3 well was preparing to drill ahead at 1,120 meters (3,674 feet) true vertical depth sub-sea.” Comment: “ preparing to drill ahead” probably means they have just set casing at 1,120 meters true vertical depth sub-sea. I no longer know what the casing program is. IOC used to set the 13 3/8” casing at this depth. So that could be it. OSH said that we finished the hole at Antelope-5 with a 6” hole so that could mean that they are now using a different casing program with 7” casing set at the top of the reservoir. We will not know until they tell us. Their latest map shows that they expect to find the top of the reservoir at ~2,000 meters TVD sub-sea. So if the map is correct they have about 880 meters to drill before reaching the top of the formation. The gas/water contact they are currently using is -2,214 meters TVD sub-sea . So if the map is correct we will have 214 meters (702 feet) of some kind of formation above the gas/water contact or a 214 meter gas column. I believe it is possible the well will come in a bit higher than prognosis and I am hoping to find some good porosity limestone above a zone of dolomite. IOC is expecting some lower porosity dirty “lagoonal” limestone, probably containing shale and silt. So they have low expectations for this well. They say: “proposed total depth of around 2,464 meters (8,084 feet) true vertical depth sub-sea.” so they plan to drill the well 250 meters (820 feet) below the gas water contact. 3. “The PRL15 joint venturers are discussing an additional appraisal well to the west of Antelope-5. The decision whether to drill a further appraisal well will follow the evaluation of the Antelope-6 appraisal well and the results of the latest flow test at Antelope-5. “ Comment: If they wait until Antelope-6 is drilled and evaluated to make the decision to drill Antelope-7 that means that they will not start building the location for Antelope-7 until after drilling at Antelope-6 which could be around April 1st. I believe it would take them at least four months to build the location and move in the rig and then three months to drill the well. So the well would be completed around Nov. 1, 2016. If they start the certification process after completing Antelope-6 we could receive the interim resource payment in the 3 Qtr of 2016 or about 4 months (120 days) after completion of Antelope-6. If they choose to drill Antelope-7 before starting the certification process we will not receive the interim resource payment until about the end of the first Qtr. 2017 but the payment will likely be larger than if we do not drill Antelope-7. RE: Comments on the latest Press Release - Putncalls - 01-23-2016 Wouldn't a .35 PSI drop indicate there is a minimum of 750/0.0001 MMCFs of gas or a measly 7.5 Ts?. (Boyle's law) RE: Comments on the latest Press Release - Stavros - 01-23-2016 Why spend months and tens of million$ drilling A-6 (and possibly A-7) and then spend million$ and take another 4 months to hire two experts when Putz already knows how little gas is there? IOC already informed the market that the GLJ high case estimate is now their internal mid case estimate ... far higher than 7 tcf! OSH has also intimated that they will be obliged to pay IPI investors far more $cratch because E/A contains measurably more than 7 tcf. Is this the latest Short's attempt to scare IOC Shareholders? RE: Comments on the latest Press Release - Putncalls - 01-23-2016
'Stavros' pid='66168' datel Wrote:Why spend months and tens of million$ drilling A-6 (and possibly A-7) and then spend million$ and take another 4 months to hire two experts when Putz already knows how little gas is there? IOC already informed the market that the GLJ high case estimate is now their internal mid case estimate ... far higher than 7 tcf! OSH has also intimated that they will be obliged to pay IPI investors far more $cratch because E/A contains measurably more than 7 tcf. Is this the latest Short's attempt to scare IOC Shareholders? Excuse et moi se vous plais. I used 7.5E12 CF as a minimum. I have no idea how many STD DEVs that is, from the mean. RE: Comments on the latest Press Release - katytrader - 01-23-2016
'Putncalls' pid='66169' datel Wrote:Bad French does not inspire confidence in your argument. lol RE: Comments on the latest Press Release - Relker - 01-24-2016
'petrengr1' pid='66164' datel Wrote: What is the reason why they drill under GWC? RE: Comments on the latest Press Release - jft310 - 01-24-2016 AAPG Figure 1 Contact definitions and relationship of contacts in a pool (right) to reservoir capillary pressure and fluid production curves (left). The free water surface is the highest elevation with the same oil and water pressure (zero capillary pressure). The oil-water contact corresponds to the displacement pressure (DPdrill pipe) on the capillary pressure curve. The transition zone is the interval with co-production of water and hydrocarbons. The fraction of co-produced water is shown by the dashed line on the left. The gas-oil contact is controlled by the volume of gas in the trap, not the capillary properties. Positions of initial fluid contacts are critical for field reserve estimates and for field development. Typically, the position of fluid contacts are first determined within control wells and then extrapolated to other parts of the field. Definitions of fluid contacts are based on comparison to capillary pressure curves (Figure 1). The free water level is the highest elevation at which the pressure of the hydrocarbon phase is the same as that of water. The hydrocarbon-water (oil-water or gas-water) contact is the lowest elevation at which mobile hydrocarbons occur. The transition zone is the elevation range in which water is coproduced with hydrocarbons. The gas-oil contact is the elevation above which gas is the produced hydrocarbon phase. RE: Comments on the latest Press Release - MartiniStocks9756 - 01-24-2016 I have a a few questions. By the way the detailed discussions on the well results and well tests are phenomenal and certainly shows the engineering expertise here but, I am just a novice and would like to know the following: 1. If A7 is drilled why would it add so much in understanding that the 6 wells already would not show? And to add to that discussion would we not receive the extra payment of molecules with the final evaluation allowed by the Agreement just a few years later? So in the long run we get paid on information the A7 well shows down the road. So even though it is another six months or so to wait why not take the certification money as soon as possible and continue the exploration. 2. Since we like to speculate, why hasn't Hession cut a deal for TBR? That would be a boost to the stock PPS. No offers yet? Or just not the right deal? 3. If the company is to receive an offer on a buyout and most here want to say that they have to pay on the certification dollars, but why would they not also have to pay on the 9 billion opportunity the gas plant provides and TBR discoveries and the other acreage. So what some are saying right after certification they can steal the future assets for a song. Not sure I get that but do believe that could be the case because I have seen these buyout deals take care of the management team and leave the shareholders holding the proverbial bag. So since we have a minimum seven to nine month wait at the moment I think these discussions are great! Look forward to hearing more. RE: Comments on the latest Press Release - Putncalls - 01-24-2016
'MartiniStocks9756' pid='66176' datel Wrote:I have a a few questions. By the way the detailed discussions on the well results and well tests are phenomenal and certainly shows the engineering expertise here but, I am just a novice and would like to know the following: 1. If A7 is drilled why would it add so much in understanding that the 6 wells already would not show? And to add to that discussion would we not receive the extra payment of molecules with the final evaluation allowed by the Agreement just a few years later? So in the long run we get paid on information the A7 well shows down the road. So even though it is another six months or so to wait why not take the certification money as soon as possible and continue the exploration. 2. Since we like to speculate, why hasn't Hession cut a deal for TBR? That would be a boost to the stock PPS. No offers yet? Or just not the right deal? 3. If the company is to receive an offer on a buyout and most here want to say that they have to pay on the certification dollars, but why would they not also have to pay on the 9 billion opportunity the gas plant provides and TBR discoveries and the other acreage. So what some are saying right after certification they can steal the future assets for a song. Not sure I get that but do believe that could be the case because I have seen these buyout deals take care of the management team and leave the shareholders holding the proverbial bag. So since we have a minimum seven to nine month wait at the moment I think these discussions are great! Look forward to hearing more. 1. A7 may be due to the current oversupply of fuel 2. No reason to sell TBR into a fire sale 3. Someone else might help with this one. RE: Comments on the latest Press Release - Palm - 01-24-2016 #3 is elementary. Who's going to pay today for a hamburger tomorrow? The prospects, the plants etc. are an aberration. They don't exist in a business sense and any buyer has to take the risk and provide the capital for them to become a reality. IOC has done very little at this point to bring them to market (ie a viable cash PRODUCING entity). It would be like me asking you to pay me a $5 million for a house on the beach when I only have the rights to the land on which to build it. |