Two LNG developers at loggerheads
The Elk Antelope project in the gas fields of Gulf Province has ran into some conflict which is still being sorted out by way of an international Arbitration between Oil Search and InterOil.
From the government’s point of view according to Petroleum and Energy Minister Nixon Duban Petroleum Retention Licence 15 will be reviewed next year and operators will be asked to show cause and not prolong the project by way of dispute.
The conflict arose in March this year when interOil sold its 40 percent stake in the gas project to French company Total.
The dispute surrounds stakes in the Elk and Antelope fields, coveted because the gas could be used either for a possible expansion of the $19 billion liquefied natural gas (LNG) project that ExxonMobil Corp is heading.
Total and InterOil want to use the gas from the fields for a new LNG plant that would be competing with Exxon Mobil.
Minister Duban says PNG needs the Elk Antelope and according to government plans it should begin work between 2020 and 2021.
**********
Total develops concept
By SHIRLEY MAULUDU
FRENCH companyTotal is in the process of selecting a development concept for the Elk and Antelope gas fields in Gulf, a company representative says.
Total E&P PNG Ltd managing director Philippe Blanchard told The National that: “We are still progressing on the selection of a development concept for Elk/Antelope.
The firm’s entry into exploration in Papua New Guinea became official after it signed the farm-in rights deal with InterOil in December last year.
Depending on the exploration results, this could lead to a final investment decision by 2016 for the development of the gas fields and the construction of a liquefaction plant located onshore of Gulf.
Total had said it would leverage its technology and experience in major LNG projects to reinforce its long-term production post-2020.
Blanchard said last week that investment values for the Gulf project would be revealed after Total had a project model in place.
However, the firm had said in a statement: “Total will pay US$470 million (K1,183m) for a 42% interest (32.5% if the government executes its option to join the project) with a contingent payment estimated by Total at approximately US$590 million (K1,486m). The transaction remains subject to the approval by the PNG government.”
Total’s executives visited the country earlier this month to emphasise their commitment towards the project.
Prime Minister Peter O’Neill has welcomed the company’s commitment to advance PNG’s second LNG project.