I see no indication whatsoever that Total is trying to delay certification in any manner. That is simply not a fact. Drilling is continuing on Ant 4, and that rig will move to Ant 6 upon completion. Total indicates that the appraisal program will be complete by year end 2015. Thus, somewhere around Dec 31, 2015 will be the 'trigger date' for certification under the Total/IOC SPA. Approximately 120 days after that date, Total will be required to pay IOC the Interim Resource Payment, or approximately on or around May 1, 2016. This is near to mid 2Q16.
Total cannot, under the terms of the SPA, do anything to unreasonably delay certification. As Steve noted above, Total has a fiduciary duty to act in the best interests of the JV. However, they also have a specific and enforceable contractual duty to perform certain obligations under the SPA. For example, under Section 3.4(a) of the SPA Total MUST "notify ... the Seller within five (5) Business Days of the completion of drilling (and testing) of the last appraisal well under the Appraisal Work Program." Although the end date of completion of drilling and testing of Ant 6 is under the direction of Total, as Operator of PRL 15, they must act in good faith and use reasonable business discretion that does not work to the detriment of the Seller (IOC).
Additionally, under SPA, Section 8.1(2), regarding the Appraisal program, Total must drill the 3rd appraisal well (Ant 6) in such a manner "that such additional well(s) shall not
adversely affect the parties' objective to reach FID in the shortest practicable timeframe." This clause was specifically put into the SPA to address any attempt to delay FID (and by extension, Certification) by Total, as Operator. Such a specific clause relating to 'time" in a contract is much more enforceable that the general fiduciary duty required by partners under a JVOA. This clause gives IOC specific enforceable rights under the SPA to hold Total to a timeframe for completion of Ant 6 (and thus, the declaration of the "trigger date" for certification) that does not adversely impact the stated contractual objective to reach FID as quickly as possible.
As we move forward, it is easy to forget that the actions of Total and IOC are governed by the terms of the SPA, and it was a very, very carefully negotiated contract that anticipated many (and, perhaps, all) of the issues that will arise in moving towards FID and the building of the plant. Dr. Hession and his team did a remarkable job negotiating the terms of the SPA with a Super Major and we will see the benefits of their diligent work far into the future.