'Putncalls' pid='63148' datel Wrote:If OSH is trying to conserve money can they slow down the certification process by pushing for the slow road?
Personally I don't see how OSH can slow anything down. Below are some of my thoughts:
OSH pays Pacific LNG for "overage" after the drilling/testing data is available from TOTAL and IOC who did the work. That's a contractual obligation OSH has in their agreement with Pac LNG. It has nothing to do with the appraisal/testing program being undertaken by TOTAL/IOC.
The SPA between IOC and TOTAL spells out exactly how the E/A certification process plays out (see attached).
Once all the agreed Appraisal Wells are drilled and the final piece of data is collect, they must immediately hire two independent Experts to do the evaluation. So TOTAL can slow down the process if they so choose.
Today TOTAL have 12 million ton per annum capacity; they want 20 million by 2020.
BUTT ... I can't fathom how TOTAL plan to get there without counting Papua LNG because ...
1. The 6.7 million ton per annum Balhaf LNG plant in Yemen is shut down so NO CASH FLOW from the 40% owned by TOTAL (2.7 million tpa); Ergo they cannot currently produce the target of 12 million per year. Will it ever come back on stream and be a reliable LNG production sourse for TOTAL?
2. The upcoming Ichthys LNG Plant is 8.4 million tons per year; TOTAL has 30% share. That comes to 2.5 million tpa of the 20 million tpa capacity they plan to have by 2020. That's a measurable part of the +8 new capacity they want to start up by then
3. The Yamal LNG Plant in Russia will EVENTUALLY be three trains, each at 5.5 million tons per annum. In the Investor's Day Meeting Patrick Pouyanne stated very clearly that the three trains will come onstream consecutively. He refused to say when the first one would start up. He only said that overall "Progress" of Train 1 is 30%. Currently they are struggling to get financing and then complete its construction by the end of 2017. TOTAL has 20% ownership, which comes to 1.1 tons per annum per train.
SO ... how the heck do they get to 20 million tons per annum by 2020? There are many options in the LNG universe. Three of them are:
1. Aggressively go ahead with Papua LNG and start it up by the end of 2020. It can theoretically be done if they reach FID by 3Q2016. Their 40% share would be 2.5-3.5 million tons per annum depending on the final size. ==> POSSIBLE
2. Buy out Santos from PNG LNG (16%) and immediately get roughly 1.1 tons per annum LNG production. ==> POSSIBLE; but they would be foolish to acquire Santos itself with their bad Australian investments in coal-based gas
3. Acquire OSH (29%) and thereby get their 2 million tpa share of PNG LNG ==> NOT LIKELY