Issue is that Exxon and PNG want and need gas NOW. Why? Because getting the process started now will end up with LNG in 2017. One year for FEED/FID and 2 years to build. This is at a minimum. The PNG government wants it as soon as they can for revenue growth and Exxon needs to start making preparations.
So I would say that Exxon has no time to wait for more wells to be drilled and gas to be found. That will take an extra 2 years with delineation and deals and structuring them.
There is a big tank of gas with at least 7 Ts+ in it. That will get them at least one and probably 2 trains in 2017 at the earliest.
So I would say that Exxon has no time to wait for more wells to be drilled and gas to be found. That will take an extra 2 years with delineation and deals and structuring them.
There is a big tank of gas with at least 7 Ts+ in it. That will get them at least one and probably 2 trains in 2017 at the earliest.