'johnwgrant' pid='44594' datel Wrote:
'petrengr1' pid='44590' datel Wrote:From an earlier post:
“The closest IOC well to Wahoo was Black Bass-1. It was drilled to a depth of 5,953 feet. Black Bass-1 was spud on Apr. 25, 2005 and was completed by July 18, 2005.”
That is about 84 days and they were probably drilling in a less problematic area and did not run down-hole deployment valves which takes time. They set 9 5/8” casing at 1,178 feet and 7” casing at 3,100 feet and did not run casing in the bottom 2,853 feet of the hole. So, at Wahoo we will be doing a lot of work that was not done at Black Bass-1 and, therefore, we should expect it to take a longer time.
The second and third Qtr. MD&A for 2005 indicates that the cost to drill Black Bass-1 was about $7 million using a contract rig.
The presentation at http://tinyurl.com/ldbgxm9 page 12 indicates Wahoo-1 should take 60 days and cost $50 million using a Company owned rig (Rig 3).Now there's inflation for ya' !!!
But,we must remember as we are told almost every day,that our inflation rate is only about 2% (according to our Fed). I'm sure they arrive at that # because they never do any of the following: buy food,buy gas,pay any college tuitions,go to a dentist or pay any hospital charges......let alone drill a o/g well. Go figure!