03-06-2012, 08:37 AM
Getit - correct, that's what I also got from slide 19.
Here's my revised estimates based on today's data, plus what we've previously been told:
- Conduct VSP
- Run 9-5/8" tie back w/DDV:
March 13 "7-10 days from today"
- Install pressure managed equipment
- Test BOP
- Drill into reservoir 200-300'
- Conduct DST
March 21
- Drill to prognosed TD ~7,572'
- Run wireline logs & test
- Take rotary sidewall core plugs
- Complete well
May 15
Of course I don't know the underlying durations of each activity, but at a macro level it does look like if things go well they may have a DST for us by the 4Q CC coming up week of the 19th.
For now, I'm sticking with a mid-May target date for completion, but certainly major issues (or lack of) will influence final date.
Here's my revised estimates based on today's data, plus what we've previously been told:
- Conduct VSP
- Run 9-5/8" tie back w/DDV:
March 13 "7-10 days from today"
- Install pressure managed equipment
- Test BOP
- Drill into reservoir 200-300'
- Conduct DST
March 21
- Drill to prognosed TD ~7,572'
- Run wireline logs & test
- Take rotary sidewall core plugs
- Complete well
May 15
Of course I don't know the underlying durations of each activity, but at a macro level it does look like if things go well they may have a DST for us by the 4Q CC coming up week of the 19th.
For now, I'm sticking with a mid-May target date for completion, but certainly major issues (or lack of) will influence final date.