As everyone knows, conversation is ongoing re: drilling Ant 7 prior to certification. I hope to shed some light on the IOC mindset with this course of action. First, there are always pros and cons. Let’s start with the cons:
-
Cons
-
Delay in certification payment
- 3-9 months
-
Cost to drill
-
It was communicated to me at the AGM that IOC would own this drilling cost
- For the record, that doesn’t make sense to me as I would think the JV would share this cost, anyways, moving on
-
It was communicated to me at the AGM that IOC would own this drilling cost
- Potential to add no discernible increase in resource size
-
-
Pros
- Potential increase resource to size
Now, when I pointed out at the AGM that 1st quarter cert payment might end up being 2nd quarter 16*, Hession responded that I should be more worried about every potential molecule of gas as opposed to timing. Fair enough, I think it gives a pretty clear answer into how the company is thinking – more gas > time delays to cert payment. So, the question then becomes, why is every extra gas molecule so important? To answer this, I think there are 2 things to consider:
-
Current project FID timeline of 2nd quarter 2017
- Drilling Ant 7 will have zero impact to pushing out the FID date
- Operational cash until 2021 LNG plant go live
To determine necessary operation cash lets calculate our expenses first (high level back of napkin approach):
-
Expense Details
- LNG Plant: 16 billion times 36.5% IOC interest times 30% cash down = 1.752 billion
- Drilling**: 4 wells/year at 50 million/well times 6 years = 1.200 billion
- Seismic***: 50 million/year times 6 years = 300 million
- Other: 25 million/year times 6 years = 150 million
- Total Expense: 3.4 billion
So what is our income:
-
Income Details
- Current Cash: 394 million
- Certification payment: Assume 9.9 Tcf = 1.717 billion
- FID payment: 517 million
- Total Income: 2.628 billion
772 million shortfall - through to 2021. This could be addressed by:
-
Farm-in deals
- not good unless prospect is proven up based upon what we saw from the Total deal any their unwillingness to pay for gas potential
-
Dilution
- 25-40% dilution – ouch!
-
Don’t drill Tri, Wahoo, Raptor etc
- Now we wait 5 more years before additional trains are added or juicy farm in deals are completed
-
Spend an additional 3-9 months and drill Ant 7 and Ant 8 if necessary
- 400 million for every extra Tcf over 7 Tcf
- No impact to FID date or LNG plant go live
So, if we choose option 4 and certify 12 Tcf instead of 10 Tcf – our 772 million dollar shortfall disappears. After seeing this, I believe I know why Hession said that I should be more worried about every potential molecule of gas and why he isn't so worried about my above listed negatives. But that is just me, you decide.
p.s. I also confirmed that they will not drill Ant 7 unless they feel it will add >= 1 Tcf to the resource size and of JV approval.