'3 additional high-returning LNG trains'
#15
Palm-Most likely he was saying 2 trains to start and more after that hopefully . Since PNG is still a 3 rd world country assuming what's in the press as being reported accurately even with quotes may be a push . I was the one who contacted IR and got the answer I gave you . So I know what IR stated.
Hard to believe ONeil got it wrong in his journal about an Antelope/Total 3rd train . But maybe he had someone else write that journal entry for him . Could have happened that way.

Here's how Cheniere Energy did its 6 train build . Two trains to start with a plan to build six. The second build trains 3 and 4 were stated less than a year after the first 2 .
When someone says 3 trains does not mean they all start construction at the same time .
Could build out Antelope similar to Cheniere just with a staggered start .

Sabine Pass Liquefaction, LLC, a subsidiary of Cheniere Energy Partners, L.P. (Cheniere Partners), is developing natural gas liquefaction facilities at the Sabine Pass LNG receiving terminal located in Cameron Parish, Louisiana adjacent to the existing regasification facilities. The Sabine Pass site can readily accommodate up to six liquefaction trains capable of processing over 3.5 Bcf/d of natural gas. The production capacity of each LNG train is being designed for approximately 4.5 mtpa. The 1000+ acre Sabine Pass site is strategically situated to provide LNG export services given its large acreage position, proximity to unconventional gas plays in Louisiana and Texas, its interconnections with multiple interstate and intrastate pipeline systems, and its premier marine access less than 4 miles from the Gulf Coast. The trains are being developed in three stages, with stages including Trains 1&2, Trains 3&4 and Trains 5&6.

Cheniere estimates that construction of the liquefaction capacity is competitive due to expansion economics, since the Sabine Pass LNG terminal already has many of the facilities required for an export terminal. Sabine Pass Liquefaction will have access to the existing infrastructure, including five storage tanks and two berths at the Sabine Pass terminal, as well as Cheniere Partner’s 94-mile Creole Trail Pipeline, which is being reconfigured to reverse the flow of natural gas, making it a bi-directional pipeline.

Construction commenced on Trains 1&2 in August 2012. Construction commenced on Trains 3&4 in May 2013. The first LNG train is expected to produce LNG in late 2015, with the remaining three LNG trains being
Reply



Messages In This Thread
RE: '3 additional high-returning LNG trains' - by jft310 - 06-30-2015, 03:17 AM