(07-02-2015, 11:56 PM)AU74 Wrote:I was just looking at the IOC milestone chart from January to compare to today's news. I'll be ignoring the Eeyore comments on here that are calling this a six month slip, then a nine month slip (who knows what the next doom and gloom accusation will be). Looks more like the project is on schedule to me.
AU74, I agree. I think that the disappointment that is being voiced on this board is due to the lack of engineering experience on large scale projects like this. What was completed so far is the Papau LNG design criteria and the amount of work that went into this was enormous. Probably several volumes long including data and analysis of numerous options and the rationale why this option was chosen, because each decision made will have multi million dollar cost impacts. Think about what the engineers had to think about for the plant locations during the construction and operation phase:
- Power requirements.
- Fresh water supply
- Geology of plant areas.
- Waste water treatment processes.
- Worker ingress and egress.
- Material laydown areas and transortation to and from these areas.
- Construction worker living areas
- The weather and it's impacts on transport.
- The most economical means to transport the gas and condensates to the facilities from both a capital and operational cost perspective.
- Level 2 schedules associated with the location and construction of the facilities.
- Let alone getting some political support of the selected locations.
So while it may appear that there has not been alot of work completed to reach this decision, there has actually been a great deal. After we determine the resource, as Stavos has said, we will be off and running at a very fast pace.
Good luck longs.