'calvin grad' pid='61012' datel Wrote:Wahoo was spud on June 14. It is a sidetrack from previously uncompleted well .Sidetrack had been completed as of June 14.. Expectations would be that they would enter the pay zone in 2 to 4 weeks.. Either permeating the pay zone is not material or complications doing so are not material .
Here's my uneducated guess, fwiw.
Wahoo sidetrack spud 6/10. I figure at lower 13 3/8 casing. Lookiing back to info available, 13 3/8ht seems to be used by ioc to 3,,,-4,000 ft.. I conservatively guess 3,200 ft , Old wells of ioc drilled 105-107 ft on average, but wahoo was more challenging. So my estimate of drilling was 56 ft per day and I'll use that for new sidetrack. Now, best guess is that ioc top of formations ran around 6,500 ft. so that would be 58/59 days to top of formation. So today would be abour 46 drilling days, leaving 12 to 13 more drilling days to TOF. So that would put Wahoo into an area of some drill news by conf call mid aug......Sound okay?.....trans