This is from Total's website and explains some of their precesses in getting an LNG project up and running. Mentions getting contracts in place sometimes "well ahead of FID" but that doesn't necessarily mean at the stage Papua LNG is today. They are more than thorough as any of these Operators are.
"Total’s talent for managing liquefied natural gas (LNG) projects is on par with our prominent rank in this highly competitive industry. From securing contracts to managing the construction of LNG facilities, we possess the full range of capabilities needed to get to grips with the complexities of this unique type of development.
Large-scale Projects and Distinctive Characteristics
We have provided ample proof of our ability to meet expectations, deadlines and budgets as operator of large-scale, technology-intensive oil and gas developments, particularly in the deep offshore. While LNG projects certainly include scope for technical innovation, they also have several distinctive features that it is essential to be proficient in:
- Projects have a long development cycle, with gestation sometimes lasting more than 20 years.
- They require a consensus among partners, joint shareholders in the company that owns and operates the liquefaction plant.
- They involve many different parties and a range of cross-disciplinary expertise (gas supply, liquefaction, marketing).
- The Final Investment Decision (FID) is contingent upon the solidity of the many agreements that underwrite the economic viability of the project. Total’s involvement in numerous LNG projects — Yemen LNG being just one example — testifies to our skill in arranging and leading such projects. We can draw on our experience operating in a wide range of geopolitical and geographic environments to come to the negotiating table with tried and tested solutions that cover every phase of the project, from upstream to the LNG midstream. Our skill in managing risks and schedules constitutes the backbone of expertise needed for projects that are as complex as they are capital-intensive.
Focus – Anticipating every type of risk
All categories of risk — economic, technical, commercial, social, financial — are itemized in a formal register. For each risk, the likelihood of occurrence (from very unlikely to almost certain) and a quantitative estimate of the consequences (technical, financial and image-related) are assigned. Mitigation strategies are defined and contingency plans mapped out to address all potential problems.
This risk management tool is built into the Overall Integrated Master Schedule that coordinates all project-related activities (e.g., construction, marketing and financial transactions). The key objective of the tool is to identify critical operations at the earliest possible stage in order to deploy all the organizational, human, financial and other resources required to stay on track.
In-Depth Knowledge of Markets
You cannot become a dominant player on the LNG stage without predicting future trends in natural gas consumption. That’s because the future needs of importers necessarily determine the fate of projects on the drawing board today.
Total’s ability to determine whether it is the right time to launch an LNG project stems from the complementary skills of our teams of analysts in Exploration & Production and Gas & Power. Every year, as they consolidate their forward-looking analyses into a “global gas assessment,” they forecast trends in global gas demand for the next 20 years.
We apply our knowledge of markets to negotiate long-term LNG sale and purchase agreements, often well ahead of the Final Investment Decision on a project. Moreover, we are now almost always on the list of direct customers of the liquefaction plants in which we are an equity partner. Our capacity to market significant volumes of LNG directly makes us a partner of choice.
Managing Complex Contractual Frameworks
An LNG carrier loading its cargo at Qatargas 2.
Many different parties are involved in bringing an LNG project to life, including host country authorities, communities neighboring the project site, natural gas suppliers, the liquefaction plant operating company, the liquefaction technology owner, shipping companies, contractors that design and build the project, and gas purchasers. Assembling the many pieces of this vast puzzle entails a highly structured set of contracts combining commercial law, tax law, public and private international law, not to mention construction law and competition law.
As it advances from one phase to the next, a project gives rise to hundreds of contracts. The key agreements are:
- The gas supply agreement.
- The gas transmission agreement (from the field to the plant).
- Contracts between the shareholders/partners in the project, particularly to establish the entities that sponsor the project and for project financing.
- LNG sale and purchase agreements.
- Shipping agreements (shipbuilding contracts and charter parties).
- Regasification contracts.
Focus – Angola LNG Contracts
- Gas supply and transportation to the plant: five executive orders, 90 contracts, 50 contracting parties.
- Legal, tax and customs systems governing the plant and its production: three legislative bills, approximately 20 regulatory agreements at the ministerial or other level.
- Project governance and financing of operations: establishment of five companies entailing 200 agreements with shareholders or third parties.
- Minefield clearance and site preparation, licensing of the liquefaction technology, construction: more than 50 contracts signed with as many contracting parties.
- Lifting of the LNG, shipping, regasification, transmission: 50 contracts with 50 different contracting parties.
A Reputation for Operational Expertise
Through our involvement in numerous LNG projects,
we have demonstrated our ability to arrange and
manage these large-scale undertakings. Here,
Yemen LNG.
Due to the sheer scale of the undertaking, building a liquefaction plant is really a project within a project. It entails selecting the site, readying it for the extensive onshore and offshore infrastructure, mitigating all the impacts, contributing to improvements in living conditions for neighboring communities, and managing colossal construction projects — sometimes in extremely remote regions.
Total has had the opportunity to demonstrate our full scope of operational expertise in connection with the development of Yemen LNG. As the main shareholder, we were the technical and commercial leader of the project.
From the earliest stages, the project’s technical concept was defined and coordinated with a comprehensive plan to mitigate its potential impacts and preserve the environment. The 320-kilometer-long pipeline corridor bypassed farmlands and other areas of importance to local communities. Offshore, the 1,500 coral colonies most exposed to the future rotations of LNG carriers were transplanted. This highly successful operation marked a world first on such a large scale.
In 2005, the Yemeni authorities approved the development plan proposed by Total and our partners. Four years later, the first liquefaction train came on stream, and the plant ramped up to full capacity with the start-up of its second train in 2010. This feat required the construction of a veritable city with the capacity to accommodate the nearly 10,000 people mobilized for the project in an extremely remote site, completely lacking in infrastructure of any kind."
- See more at: http://www.total.com/en/energies-experti...XytRh.dpuf