Behaving Like Giant - Morgan Stanley Report - June 12-15
#7

60 days for Ant 4 from August 20 = October 20

+ 30 days to move rig to Ant 6 = Nov 20

60 days for Ant 6 = Jan 20

+ 30 days to move rig to Ant 7 = Feb 19

+ 60 days for Ant 7 = April 21

+ 60 days to certify = June 20

+ 10 days to certification payment = June 30


Of course with multiple rigs going this is shorter, but...

Underpromise and you come out pink...