'ArtM72' pid='65548' datel Wrote:Isn't it true the resource Päyment comes in two 50% installments, the second half at FID? That's what I read in the SPA anyway.
Not quite correct. There are many additional payments delineated in the SPA: The next upcoming payment is the Interim Resource Payment, which is a variable amount depending on the amount of gas certified by the appraisal process. For example: if 7.1 tcfe is certified, this IRP will be $907.1 million, which will be payable within 10 days after the appraisal reports are filed with IOC and Total [appraisal reports are due 90 days after the trigger date, which is the end date of the testing of the appraisal wells). The second upcoming payment is a fixed payment which is payable at FID, and which is set at $698.71 million.
Thus, if 7.1 tcfe is certified, the total of the two payments will be $1,605.81 billion, with this total increasing with higher certified gas amounts, payable at $1.00/mcfe. All indications are that the total certified amounts will be significantly higher than 7.1 tcfe, and thus, the IR payment portion will be higher as well.
Also, don't forget that there will also be a First LNG Cargo payment of $100 million; a later Final Resource Payment and that there may also be a Discovery Bonus payable under the SPA of $100 million/tcfe for any gas discovered within PRL 15, but outside of the existing PRL 15 E/A field (ie. Ant South). [Source: Total/IOC SPA: Schedule 6: Determination of Interim Resouce Payment and Final Resource Payment]