VERY Best Case Scenario (without Ant 7 approval) without any intervening problems (somewhat low odds for that)
Total days drilling in 2015 since spud (estimated) =8
Depth on January 1, 2016 = 512 meters
Drilling rate so far (2015) = 64 meters/day
Estimated days to total depth at current rate (without any other variables) = 42
Estimated date to total depth (without any other variables) = February 2
Testing and completion of Ant 6 best case = 30 days (March 4)
Trigger date (within 5 days of completion of testing of final appraisal well) = March 9
Appraisal certification completion (90 days) = June 10
Interim Resource Payment (10 days after Interim Resource Certification) = June 20
Days to Interim Resource Payment = 163