01-08-2016, 01:10 PM
The information in this article is not fully informative regarding timing of first gas.
The article says: " ... with potential for first gas in 2022."
The facts are:
+ Page 9 of the Goldman Sachs presentation quotes the August 2015 Wood Mackenzie "assumption" that first gas would be sold in mid-2022. This is what's alluded to in the Article.
HOWEVER ...
+ On Page 11 of the Goldman Sachs presentation, IOC super-imposed their own arrow onto the Wood Mackenzie Global LNG Demand-Supply graph, showing they believe first gas will be produced in mid 2021.
In addition, TOTAL's timeline for Project Development, issued in December 2013, also showed first gas in mid-2021. To my knowledge, TOTAL has never issued a revised project schedule that indicates first gas later than mid-2021. In their September Investor's Day presentation they only stated that Papua LNG production would commence after 2020.
If Antelope 6 is the last exploration well, certification payment will be made before 4Q2016, there will be early design/construction work in 2016/2017, and FID will be in mid 2017.
If that turns out to be the case, I personally believe that first gas will be in mid-2021 after a 48 month project construction duration.
The key is whether TOTAL can sell the LNG as quickly as anticipated. With strong positive vibrations from Japanese leaders, I think it's possible they sell the LNG even faster.
There is even the potential for TOTAL to copy one of their previous LNG plant designs and get Papua LNG built faster than 48 months.
IF THEY AGREE TO DRILL A-7, then all bets are off on timing!
The article says: " ... with potential for first gas in 2022."
The facts are:
+ Page 9 of the Goldman Sachs presentation quotes the August 2015 Wood Mackenzie "assumption" that first gas would be sold in mid-2022. This is what's alluded to in the Article.
HOWEVER ...
+ On Page 11 of the Goldman Sachs presentation, IOC super-imposed their own arrow onto the Wood Mackenzie Global LNG Demand-Supply graph, showing they believe first gas will be produced in mid 2021.
In addition, TOTAL's timeline for Project Development, issued in December 2013, also showed first gas in mid-2021. To my knowledge, TOTAL has never issued a revised project schedule that indicates first gas later than mid-2021. In their September Investor's Day presentation they only stated that Papua LNG production would commence after 2020.
If Antelope 6 is the last exploration well, certification payment will be made before 4Q2016, there will be early design/construction work in 2016/2017, and FID will be in mid 2017.
If that turns out to be the case, I personally believe that first gas will be in mid-2021 after a 48 month project construction duration.
The key is whether TOTAL can sell the LNG as quickly as anticipated. With strong positive vibrations from Japanese leaders, I think it's possible they sell the LNG even faster.
There is even the potential for TOTAL to copy one of their previous LNG plant designs and get Papua LNG built faster than 48 months.
IF THEY AGREE TO DRILL A-7, then all bets are off on timing!
Drivel Maven with Personality