Back on August 20 I laid out this potential very aggressive schedule of going ahead with Ant 7. Was told I was probably a good bit off.....
"A week ago High-Arctic released 2Q 2015 earnings and one of the comments related to Rig 116: "Rig 116 recently arrived in PNG and upon clearing customs will be mobilized to a yard where it will stay until the customer completes their assessment of several different drilling locations to determine the first well site. The rig will collect stand-by revenue in accordance with the terms of the contract until it commences drilling, which is expected in early in 2016, at which time the two year contracted term will begin."
So let's say 1Q 2016 and pick Feb 1 as spud date. If we use the very quick schedule of Ant 5 for Ant 7:
1. Took 64 days to get to TD (Feb 24th)- gets us to Apr 5th
2. Total Testing was done approx. Apr 15 since they started the flow test Apr 27 with Ant 5; 47 days- gets to approx. May 22
3. Flow testing done for a couple of weeks; gets us to Early June (5th or so).
4. Say they immediately Under Part 6 move into Certification. Must each nominate Expert within 20 days- Let's say 10. Gets us to mid-June.
5. Experts have up to 90 days to get report done. They fly and take 45 days. Gets us to End of August.
6. Each Party to SPA has up to 14 days to make formal submissions. Let's say 7 days. Gets us to first week of Sept.
7. Experts have 7 days to respond. Let's say 3. Gets us to approx. Sept 10.
8. Payment must be made within 10 business days- Whew! with a near-perfect schedule we MIGHT get Certification pmt near end of Q3. Maybe.
I think based in High-Arctic's statement (owners of the rig), using Rig 116 and with a very aggressive drilling, testing and Certification process we have a shot at hitting the 3rd qtr with Certification."
Sigh........
"A week ago High-Arctic released 2Q 2015 earnings and one of the comments related to Rig 116: "Rig 116 recently arrived in PNG and upon clearing customs will be mobilized to a yard where it will stay until the customer completes their assessment of several different drilling locations to determine the first well site. The rig will collect stand-by revenue in accordance with the terms of the contract until it commences drilling, which is expected in early in 2016, at which time the two year contracted term will begin."
So let's say 1Q 2016 and pick Feb 1 as spud date. If we use the very quick schedule of Ant 5 for Ant 7:
1. Took 64 days to get to TD (Feb 24th)- gets us to Apr 5th
2. Total Testing was done approx. Apr 15 since they started the flow test Apr 27 with Ant 5; 47 days- gets to approx. May 22
3. Flow testing done for a couple of weeks; gets us to Early June (5th or so).
4. Say they immediately Under Part 6 move into Certification. Must each nominate Expert within 20 days- Let's say 10. Gets us to mid-June.
5. Experts have up to 90 days to get report done. They fly and take 45 days. Gets us to End of August.
6. Each Party to SPA has up to 14 days to make formal submissions. Let's say 7 days. Gets us to first week of Sept.
7. Experts have 7 days to respond. Let's say 3. Gets us to approx. Sept 10.
8. Payment must be made within 10 business days- Whew! with a near-perfect schedule we MIGHT get Certification pmt near end of Q3. Maybe.
I think based in High-Arctic's statement (owners of the rig), using Rig 116 and with a very aggressive drilling, testing and Certification process we have a shot at hitting the 3rd qtr with Certification."
Sigh........

