Total is 2nd in world to Shell for LNG. They know what they are doing.
Posts: 6,851
Threads: 697
Joined: Dec 2011
Reputation:
441
Yes Art they are initial IOC published estimated timelines. The problem is (and the lesson we should have learned by now) people here set these in stone and absolutely expect them to happen. They don't work that way. I used to make that same mistake until talking to people in the industry who have been there and done that. Investors/SEC/Wall Street demand timelines, so we get what they give us. They'd prefer to not have to say as much as they do because they know sometimes things will go faster and other times slower. Just the way it is. I no longer take these as anything more than estimates, and optimistic at that.
Posts: 2,904
Threads: 58
Joined: Mar 2012
Reputation:
259
Palm -
I'll give you they are initial TOTAL timeline estimates. It is also true that time lost on critical path items add to the project endpoints. It is unlikely anyone here knows what their project schedule looks like, but a six month delay in the start of FEED doesn't look too good from my perspective.
If anyone following this stock for more than a year believes anything IOC says or does is set in stone they must be thinking about well casings.
Posts: 2,505
Threads: 219
Joined: Dec 2011
Reputation:
109
It's not that bad Art. It's really a lot better than it was. There is still a lot of engineering that can be done without bank quality certification numbers. The 2014 drilling program did not go well and we got the A4 delay. IOC managed that so that the only thing limiting certification is expanding the volume estimate. The FID date hasn't been changing either. That's good because it's not so much that there will be a delay, it's what are the delays as a percentage of the time to done.
Posts: 574
Threads: 27
Joined: Nov 2012
Reputation:
101
Just as time to accomplish can increase on a critical path item, it can also decrease and get back on track and still come in on original schedule or even sooner. Planners are always working on ways to meet or beat a timeline and to deal with the unexpected. None of them get a bonus for being late.
All this whining is counter-productive, IMHO.
Constant whining and bickering about things we know so little about accomplishes little except to allow the whiner to vent upon all of us. If we don't like what the company is doing, we can easily vote with our feet and sell our holdings. But then we would have to admit that our judgment was wrong and we investors don't like that.
Perhaps that's the problem with online forums. It is far too easy to act out of character. I doubt that most of the whiners here would behave that way in person. At least, that's the way it looks from here.
Posts: 2,505
Threads: 219
Joined: Dec 2011
Reputation:
109
I think it's it fair to discuss the things that don't or might not work out well. It's good to fully understand the risks. The only way I know of to beat wall street at it's game is to know the company and non of them are perfect.