'Stavros' pid='57331' datel Wrote:If you click on the picture of this fellow "Apthalie Kep" you'll find that he posted twice on Twitter. He said the following: 1. "In Papua New Guinea on the 27/04/15 #InterOil Ltd is inviting Prime Minister Peter O'neil to open the firing/ testing of Antelope#5 LNG." Then he posted this 14 hours later: 2. "Antelope#4 was shut down due to huge amount of muds underneath the drill hole.##PNGLNG Gulf##" So who is this guy and what do his posts mean? MY THOUGHTS: The truck he's leaning on has this company name on the door: "Pagini Sakura Transport Limited" The following March 5 Article has some background information on them: http://www.pngloop.com/2015/03/05/milest...r-company/ + Sakura Osura Resources Investments Limited (SORIL) has now taken control of the administration of payroll, insurances, and NasFund for all casual labour and assistant foremen previously managed by Oilmin (an Interoil Contractor). + SORIL provides labour to Oilmin for Herd Base camp services. Local community people employed after induction have to date been managed by Oilmin. This new arrangement will now be rolled out through the other camps within PRL 15 where Oilmin operates. + A joint venture with Pagini in transport and logistics as further examples of SORIL activity. So what can we say .... 1. It's very likely that this "Tweeter" still works for SORIL. Possibly he's been invited to be at the Antelope 5 drill site on Monday to watch PM O'Neill open the firing/testing of PRL15. So I believe this to be a planned event for Monday. 2. To my opinion, it's very unlikely that the revelation of Antelope 4 being shut down due to a "huge amount of mud underneath the drill hole" is of any concern whatsoever. o Antelope 4 shut down - - - probably true. o Huge amount of mud underneath the drill hole - - - not very specific information. Perhaps they have an issue with disposal of the normal amount of mud/solid waste that's created when drilling? Maybe Petreng1 can comment on this?
1. "Antelope#4 was shut down due to huge amount of muds underneath the drill hole."
I have no idea what this means. They could have been using managed pressure drilling and losing a lot of water down hole. Could have had problems with the hole such as cuttings sticking the pipe due to no hole cleaning...
2. They hit the top of the formation somewhere around 1,986 meters.
3. On Feb. 28th they were at 2,002 meters.
4. On Mar. 31st they were at 2,134 meters.
5. Most of the best pay will be at the top where they have already drilled. Most of this was cored so we should have good data on porosity and permeabiliby.
6. We did not expect but about 1,000 feet of pay at this location. At least 500 feet of the best pay has already been drilled. They may or may not have reached the depth of the gas/water contact. We do not know the current depth.
7. Since the good part of the pay zone is open in the open hole they are far enough along that they could shut down the drilling and put a pressure recording device down hole for use in the connectivity test while they are producing Antelope-5.
8. Could be they do not want to further delay the connectivity test. They want to complete the connectivity test by the end on June and free up the rig at Antelope-5 for use on the next well.
9. Need to stay on schedule as close as possible so we can get the certification done and get our resorce payment before the end of the year.
10. Need to get rigs up and running at Antelope-6 and Antelope South-1. Connectivity test will not include Antelope-6.