How LNG Supply Expands w/o New Projects.
Hard lessons were learned in AU LNG by not sharing. Not to be repeated in PNG.
**********
..................PRODUCERS NEED TO COOPERATE
The first way to do this is through de-bottlenecking existing plants, a process Kavonic said delivered an average 14 percent boost in capacity at LNG plants that have implemented the efficiency measures in the past.
An additional 4 million tonnes per annum of LNG is probable and a further 6 million possible from de-bottlenecking, Kavonic told the conference.
These are fairly significant numbers, as 10 million tonnes would represent an 11 percent increase in Australia's eventual capacity and is just under half of Chinese annual demand.
The second way to boost capacity is through brownfield expansions, which Kavonic said typically cost about 30 percent less than building projects from scratch.
This could add more than 10 million tonnes in Australia, but Kavonic estimates that brownfield developments would require a price above $8 per mmBtu to be economically feasible.
A third way to boost capacity is backfill, which involves committing new gas to existing projects to allow them to continue operating beyond their expected and planned life.
While this doesn't add new capacity, it prevents volumes from leaving the market, and Kavonic estimates that 15 million tonnes of capacity could be maintained by 2030 if companies adopt backfill policies.
What becomes clear is that there are substantial volumes of LNG that can come to the market in the coming years at considerably lower prices when compared to the huge cost of developing new plants and natural gas fields to supply them.
There are of course some fairly significant hurdles, the main one being the need for the various companies in the industry to put aside rivalries and work together to share infrastructure and establish joint ventures to supply natural gas to LNG trains.
"Boys and girls don't like to share their train sets," was how Kavonic put it, a jest that rings true when looking at the three adjacent coal-seam gas to LNG plants recently built at Gladstone, on Australia's east coast.
These plants don't share infrastructure even though it would have been more cost-effective for all concerned if they had jointly developed facilities such as pipelines, storage, jetties and power supply.
Perhaps the expected period of low prices in the next few years will encourage the sort of innovation and cooperation that would allow LNG producers to increase output at competitive costs should demand grow strongly in the 2020s.