I've given this a cursory review. There's no question the well location needs to be west of A5, which has the best reefal buildup of the wells tested and was proven to be in pressure communication with Wells. 6 and 1, at least. The huge thickness of A5 suggests reservoir has to extend a good bit to the west.
Looking at existing well spacings, it appears that a distance of 2.5 Km from A5 to A1 and A5 to A6, still allows good well pressure communication. But this is all in the north - south or west to east directions from A5. A7 is roughly about 2.5 km due west from A5. The map suggests the deposition will transition from reef to slope and there will be a fault.
Moving the well too far west is the risk. It may land on the other side of the fault and miss the reservoir completely. But given the tremendously good quality of A5, it would seem there has to be reservoir a good distance to the west of A5.
A vertical well at the proposed location is probably the lowest cost. But drilling dry holes at lowest cost is not a good thing.
Phil Mulacek in his July presentation (which by the way seems to be an excellent document to use in a No with dissent vote AND/OR to use in letters to regulators to pursue illegal trading crimes committed by Hession and the board) provides a better well plan which is closer to A5 and which seeks to find the reservoir and the fault using a lateral directional drilling plan. The geological risk of his plan is greatly reduced but the mechanical risk (a more complex well) is probably greater but only after the lateral part begins. The first part of the well would conventionally penetrate the reservoir. I would take that vertical well down to the GWC, log and evaluate, then sidetrack shallow and go west to find the fault with a lateral directional well. That may be exactly the same as what Phil proposed. This seems much better than what IOC have told us to date on A7.
As I mentioned in another thread, these companies are not drilling this well with IOC shareholder interests in mind in my opinion.