Exxon’s $19 Billion LNG Project in Papua New Guinea Set to Start
#1

Exxon’s $19 Billion LNG Project in Papua New Guinea Set to Start

2014-04-08 10:07:41.605 GMT

By James Paton

     April 8 (Bloomberg) -- Exxon Mobil Corp., operator of a $19

billion natural gas export project in Papua New Guinea, said the

development is more than 95 percent complete and should be at

full capacity before the end of the year.

     Condensate, liquids recovered through the gas liquefaction

process, are already flowing, Decie Autin, Exxon’s project

executive in PNG, said today in an interview in Perth, Western

Australia, where she’s attending an industry conference.

     Shipments are expected to begin in mid-2014, ahead of

Exxon’s previous October target, and output will be raised to

capacity over the following months, she said.

     “We’re ahead of schedule, and I haven’t really heard that

from many of the other projects,” Autin said at the Australian

Petroleum Production & Exploration Association conference.

     The venture with partners including Oil Search Ltd. and

Santos Ltd., may add capacity as Asian demand for the fuel

increases, though a decision hasn’t been made, Autin said.

For Related News and Information:

Total Pays $401 Million to InterOil as Oil Search Disputes Deal

NSN N3CIAF6JTSEY<GO>

Oil Search Disputes InterOil-Total Deal in Papua New Guinea

NSN N34YEC6TTDSI<GO>

Total to Pay $401 Million to InterOil in Revised PNG Gas Deal

NSN N30ROS6K50YI<GO>

Reply

#2
"may add capacity as Asian demand for the fuel increases, though a decision hasn’t been made"

Rather odd statement. Less than a year ago they were quoted as saying that expansion of the PNG LNG plant was/is one of their highest priorities as the ROI on the 3rd train will be very high. Reports as recent as today say the same thing that we've heard for quite some time; LNG demand in Asia is quite high and expected to stay that way. So that's likely not a barrier to expansion.

High ROI, continuing high Asian demand for LNG. Two necessary ingredients in the decision process. Now the 3rd is least cost supply of gas. That has NOT been decided. The only drilling going on by PNG LNG partners right now is at Hides for their wells that will supply trains 1 and 2. Santos even in their most recent presentation said that they are well positioned for expansion due to their present ownership in the base project, but sources for future trains is uncertain.

Sure seems that once you have a project to the point where you are sure it will be at present capacity within a year you would be pressing toward a decision that allows short time to maximum ROI. But the company responsible for finding source for PNG LNG is currently not drilling anywhere in PNG. But they just bought into a PRL where they say they feel they will be able to influence the direction of development to bring the gas to market in the quickest and most economical way.
Reply

#3
In OSH's presentation at the GS Australian Investment Forum in March, they stated they were "moving forward on LNG expansion plans", with "drilling to determine size and shape of Hides underway", and with the "proven P'nyang resource" a potential source.

Has something changed since then?

So far, things are not going very well for them on their influence at PRL 15, huh? That's okay though, since they said it "provides exposure to potential new LNG development", and is "commercially attractive on both a stand alone or expansion basis".
Reply

#4
Yes something has changed. After that conference they closed on the Pac LNG interests and at an Asian conference they added "Elk/Antelope" in their list of possible sources for expansion of the PNG LNG project (slide 12). They also mention Hides Deep as a potential source (into which nary a well has been drilled yet and nothing planned until at least Q4 2014 "subject to partner approvals"). And they mention P'nyang as being 2.5Ts which is not enough for a train, in a very remote area, and currently not classified as a PNG LNG project source.

So quite a lot has changed
Reply

#5
As I stated, in the March presentation (slide 29), they stated that "drilling to determine size and shape of Hides" was "underway" as part of what they were doing in "moving forward on LNG expansion plans", which contradicted your statement that, "The only drilling going on by PNG LNG partners right now is at Hides for their wells that will supply trains 1 and 2". That is the only thing about which I was asking whether there had been a change since then, given the contradiction. Or did they just lie or make an erroneous statement about the drilling?

OSH had announced the PRL 15 deal before the March conference, and on the same slide 29 stated, as I said above, that PRL 15 was "commercially attractive on both a stand alone or expansion basis", so that listing it as a possible source for expansion of the PNG LNG project at the Asian conference was not a change.

As I also stated, they mentioned as well in March P'nyang as a potential source for part of expansion, but not enough for a train; and I was already aware of the estimate and that it is not currently an official part of the PNG LNG JV, so that none of that is a change.

There was no mention in the March presentation slides specifically of "Hides Deep", so that may be a change, unless they covered it orally as part of the general mention of "Hides" on the slide.

Therefore, not a lot has changed on what I was talking about; and the one question I raised about whether there had been a change to their claim of current drilling at Hides remains unanswered, which is okay, and not that important.
Reply

#6

I received this from a trusted friend.  Maybe I'm not the only one who needed clarification on this.

"If you look at http://tinyurl.com/qag7wna page 35 you will see that Oil Search has reported 1,572.8 BCF for their 29% share of the 1P (proven) reserves. That would mean that the total PNG LNG proven reserves are (1,572.8/0.29) 5.4 TCF. Their 2P (proven and probable) are 2,702.7 BCF giving them a total of (2,702.7/0.29) of 9.3 TCF. So if they need 4.6 TCF per train they only have enough proven reserves for 1 train. Using the proven and probable number they have enough for 2 trains."

for our cause
Reply

#7

'Li'loilady' pid='41402' d Wrote:

I received this from a trusted friend.  Maybe I'm not the only one who needed clarification on this.

"If you look at http://tinyurl.com/qag7wna page 35 you will see that Oil Search has reported 1,572.8 BCF for their 29% share of the 1P (proven) reserves. That would mean that the total PNG LNG proven reserves are (1,572.8/0.29) 5.4 TCF. Their 2P (proven and probable) are 2,702.7 BCF giving them a total of (2,702.7/0.29) of 9.3 TCF. So if they need 4.6 TCF per train they only have enough proven reserves for 1 train. Using the proven and probable number they have enough for 2 trains."

I think they assume there is enough for two trains, after all, they have sunk $19B into a plant that has built two trains. You don't build $19B plants on hope (unless you're Elon Musk).

It's the third train they're not sure about.

Reply

#8
The latest information that has not been fully updated to be current is:
http://www.oilsearch.com/Media/docs/1402...3ce4-0.pdf

"The Company’s total proven and probable gas reserves and contingent gas resources were 4,667.5 bcf, 4% lower than at the end of 2012."
Reply

#9
I think I'll just take my 18% interest from the shorts and go to Hawaii for a couple of weeks.
Reply

#10
Anyone have any short sale stats for Monday?
Reply



Forum Jump:


Users browsing this thread: 1 Guest(s)