Exxon says have been in talks with IOC on PNG LNG expansion
#1

Interesting story out this AM


ExxonMobil sees PNG LNG exports starting mid-year, below $19 bln budget


PERTH, April 9 Wed Apr 9, 2014 11:12am IST

(Reuters) - ExxonMobil Corp is on track to start exporting liquefied natural gas from Papua New Guinea by mid-year, ahead of schedule and below its $19 billion budget, the manager of the PNG LNG project said on Wednesday.

The project has started commissioning a gas conditioning plant in PNG's highlands, where the gas is drilled, a 292 kms (180 miles) onshore pipeline has been completed and the first of two units at the LNG plant is ready, project manager Decie Autin said.

First cargoes are expected mid-year, she said, declining to confirm reports that exports would start in July.

"It was going to be October. Now we think we've been able to move it up to the middle of the year," Autin told reporters on the sidelines of the Australian Petroleum Production and Exploration Association conference in Perth.

"By the end of the year I'm comfortable we'll be fully ramped up."

The project, under construction over the past five years, ran into record wet weather, steep terrain and community issues that slowed work and resulted in costs blowing out by about 25 percent from its original budget of $15 billion.

"The toughest part of the project I would tell you was the onshore pipeline," Autin said. "We had to go from 9,000 feet, up and down a tortuous path down to the shore."

The pipeline was built above ground then had to be covered with 1 metre (3 feet) of dirt to bury it for safety and security.

"This is high pressure gas pipe. You don't want anyone messing with it, because it would be dangerous," Autin said.

The first shipment is likely to be a spot cargo, rather than going to one of PNG LNG's Japanese, Chinese or Taiwanese customers, who have contracted to take 95 percent of the LNG plant's 6.9 million tonnes a year of gas.

ExxonMobil and its partners, Oil Search Ltd, Santos Ltd, Japan's Nippon Oil Corp, the PNG government and local landowners, are looking to expand the plant, but have yet to decide where to source the additional gas supply from.

Ideally they want gas from PNG's biggest undeveloped fields, Elk and Antelope, controlled by another PNG company, InterOil Corp and France's Total SA, which recently bought into the fields in a deal contested by Oil Search.

"We've been in discussions with them (InterOil) directly," Autin said, declining to comment on whether ExxonMobil still wants a direct stake in the Elk and Antelope fields.

(Reporting by Sonali Paul; Editing by Michael Perry)"

Huh

Reply

#2

Appears some posters need to pull their heads out of the hole in the sand and listen to all the clues ,now statements about negotiations. Will PRL 15 gas go to PNGLNG we don't know but for sure 100 percent it's on the table . The world is not black and white and little IOC can't be the one to divulge such talks . Anyone who thinks Interoil could be bragging about such talks is a bit naive.

Reply

#3
Decie Autin is almost as nice as the GM CEO. She just doesn't want to hurt feelings. She attributed PNG LNG's build success to 'problem solving'. One little problem needs resolving and then it's trains 3 & 4.
Reply

#4

'Palm' pid='41428' datel Wrote:

Interesting story out this AM


ExxonMobil sees PNG LNG exports starting mid-year, below $19 bln budget


PERTH, April 9 Wed Apr 9, 2014 11:12am IST

(Reuters) - ExxonMobil Corp is on track to start exporting liquefied natural gas from Papua New Guinea by mid-year, ahead of schedule and below its $19 billion budget, the manager of the PNG LNG project said on Wednesday.

The project has started commissioning a gas conditioning plant in PNG's highlands, where the gas is drilled, a 292 kms (180 miles) onshore pipeline has been completed and the first of two units at the LNG plant is ready, project manager Decie Autin said.

First cargoes are expected mid-year, she said, declining to confirm reports that exports would start in July.

"It was going to be October. Now we think we've been able to move it up to the middle of the year," Autin told reporters on the sidelines of the Australian Petroleum Production and Exploration Association conference in Perth.

"By the end of the year I'm comfortable we'll be fully ramped up."

The project, under construction over the past five years, ran into record wet weather, steep terrain and community issues that slowed work and resulted in costs blowing out by about 25 percent from its original budget of $15 billion.

"The toughest part of the project I would tell you was the onshore pipeline," Autin said. "We had to go from 9,000 feet, up and down a tortuous path down to the shore."

The pipeline was built above ground then had to be covered with 1 metre (3 feet) of dirt to bury it for safety and security.

"This is high pressure gas pipe. You don't want anyone messing with it, because it would be dangerous," Autin said.

The first shipment is likely to be a spot cargo, rather than going to one of PNG LNG's Japanese, Chinese or Taiwanese customers, who have contracted to take 95 percent of the LNG plant's 6.9 million tonnes a year of gas.

ExxonMobil and its partners, Oil Search Ltd, Santos Ltd, Japan's Nippon Oil Corp, the PNG government and local landowners, are looking to expand the plant, but have yet to decide where to source the additional gas supply from.

Ideally they want gas from PNG's biggest undeveloped fields, Elk and Antelope, controlled by another PNG company, InterOil Corp and France's Total SA, which recently bought into the fields in a deal contested by Oil Search.

"We've been in discussions with them (InterOil) directly," Autin said, declining to comment on whether ExxonMobil still wants a direct stake in the Elk and Antelope fields.

(Reporting by Sonali Paul; Editing by Michael Perry)"

Huh

HUH ??

Well, SHU readers were aware of that Big Cat's scope on the Largest Undeveloped Gas Resource in PNG.  Now that we have a hunting parties on the ground, we may expect some elephant track sightings to be trianglulated. Jump on board folks... we are going on safari.

Cheers

Tusker

Reply

#5
And this:
""The toughest part of the project I would tell you was the onshore pipeline," Autin said. "We had to go from 9,000 feet, up and down a tortuous path down to the shore."
The pipeline was built above ground then had to be covered with 1 metre (3 feet) of dirt to bury it for safety and security. "This is high pressure gas pipe. You don't want anyone messing with it, because it would be dangerous,"

IOC's pipeline to the coast will be less difficult as it has a large part in more of the lowlands. Then if the plant is built in Gulf, there is no need for the undersea. If subsea is necessary for PNG LNG expansion, they did that pretty quickly and the distance from Kerema is much less.
Then you have Wahoo which we should be getting news on in the next weeks. Very close to coast and there's already a road all the way to PM.
Reply

#6
That was a very fuzzy comment by Autin that could cover "discussions" before December or yesterday. Then when asked a more specific question, she refused "to comment on whether ExxonMobil still wants a direct stake in the Elk and Antelope fields". I've acknowledged the possibility of various outcomes, but would not change my basic opinion based on this. I'm sure IOC would hardly ever refuse to talk with Exxon, which does not assure any outcome, as before after months of "discussions", after an "agreement" even. Even if they are currently having "discussions", it could include the possibility of selling gas from outside PRL 15, which Hession has publicly acknowledged.
Reply

#7

'jft310' pid='41434' datel Wrote:

Appears some posters need to pull their heads out of the hole in the sand and listen to all the clues ,now statements about negotiations. Will PRL 15 gas go to PNGLNG we don't know but for sure 100 percent it's on the table . The world is not black and white and little IOC can't be the one to divulge such talks . Anyone who thinks Interoil could be bragging about such talks is a bit naive.

Are you referring to me, JFT?  You are welcome to name me.  See my comments above.  I have long acknowledged the possibility, but have not yet changed my basic opinion, which is well-supported and not "BS";  and I certainly do not see the world as "black and white".  Why would anyone think "Interoil could be bragging about such talks"?  Are you serious?

Reply

#8
I don't get it. How does two trains produce 7MTPA of LNG. I expested 4-5. thanks?
Reply

#9

Tusker - Loved your comment " we are going on safari" ! Maybe a 'tiger' hunting an ' elephant' . ( or when our drilling brings in more "goodies", ....maybe a couple of elephants) .

Reply

#10

'Putncalls' pid='41458' datel Wrote:I don't get it. How does two trains produce 7MTPA of LNG. I expested 4-5. thanks?

Each train was initially designed to produce 3.3 MTPA, but during construction some upgrading was done. They now will produce 3.45 MTPA, so the 2 combined should produce 6.9 MTPA.

Reply