InterOil hits obstacles with Elk-Antelope wells
By Russell Searancke Wellington
18 July 2014 00:00 GMT
Canadian independent InterOil is being challenged by downhole conditions at its big exploration programme in the Elk-Antelope area in Papua New Guinea, where its ambition is to build up additional liquefied natural gas resources.
The company is drilling three wells simultaneously — Bobcat-1 in Block PPL476 (formerly PPL 238), Raptor-1 in PPL 475 (formerly PPL 237), and Wahoo-1 in PPL 236 (formerly PPL 474).
All three are progressing slower than expected due to the complexities of the targeted Orubadi shale, which InterOil had warned beforehand could present challenges.
InterOil has suspended drilling of the Wahoo-1 well after hitting gas and higher-than-expected pressures that it considered dangerous.
Significant concentrations of methane, ethane, propane and butane have been recorded and are believed to be entering the wellbore from permeable zones above the predicted reservoir zone, which has not yet been drilled. InterOil said the pressures seen at Wahoo-1 exceeded by nearly 50% those of its Antelope discovery.
Chief executive Michael Hession said: “In exploration, we need three ingredients for success — an effective seal or cap rock that stops hydrocarbons leaking out of the reservoir, evidence of a working hydrocarbon system, sometimes called the source rock or kitchen where the hydrocarbons are made, and a reservoir, or rock that contains the hydrocarbons.”
Hession added: “We know we have two of the three ingredients at Wahoo-1. The one we have not yet proved is whether we have a reservoir and this is where we will have to be patient. Our drilling and engineering teams and expert advisers will now consider options for Wahoo.”
Drilling at Bobcat and Raptor is progressing, but slower than planned.
Bobcat also faced challenges with the Orubadi seal that resulted in two sidetracks so far.
At Raptor, drilling is understood to be just above, or at, the target zone, but is the deepest of the three wells and is progressing slightly slower than estimated.
InterOil is understood to be partnered by Total and Pacific LNG in the three wells, although Oil Search has exclusive rights to the latter’s interests.
InterOil aims to drill up to five more exploration and appraisal wells in the Elk-Antelope area in the coming 12 to 15 months as part of a $300 million campaign.
These will include the Antelope-4 and Antelope-5 appraisal wells in Block PRL 15 late in 2014 plus Triceratops-3 in PRL 39 and Antelope Deep-1 in PRL 15.
The whole ambition is to better define the size of the Elk-Antelope resources that are planned to support a LNG development.
Oil Search recently reiterated that Elk-Antelope can underpin up to two LNG trains, and the field has substantial exploration and appraisal upside.
The company repeated its view that the field contains proven and probable contingent resources of between 5 trillion cubic feet of gas and 7 Tcf, and there is a widely-held opinion it is even larger.
Oil Search bought Pacific LNG’s 22.8% interest in the field in March 2014 for $900 million.
The same month, Total finalised a deal to acquire 40.1% of InterOil’s equity in Elk-Antelope for a minimum of $540 million.
Oil Search then launched a legal action over the Total-InterOil deal, and this includes arbitration in London and injunctive relief through the PNG Courts.