Santos riding high on PNGLNG
#1
Summary
Operator Exxon Mobil was able to start up its PNG LNG plant ahead of schedule and has already ramped up to full production.
Australia firm Santos Limited has a 13.5% equity stake in the project.
Santos' YTD revenue is up 25% yoy on the back of its share of PNG LNG production (7 cargoes) in Q2.
Q3 will be the first full quarter of PNG LNG contributions, which are on-track for 24 LNG cargoes.
LNG is transforming Santos: the combination of PNG LNG and next year's GLNG start-up should cause shares to double by year-end 2015.
Santos Limited (OTCPK:STOSF) is an Australian company and the country's leading producer of domestic natural gas. In addition to Australia, the company's exploration efforts are focused on three core Asian countries: Indonesia, Vietnam and Papua New Guinea ("PNG"Wink. Operating from this base of assets, Santos is pursuing a transformational LNG strategy with interests in three large LNG projects: Darwin LNG, PNG LNG and GLNG (Queensland). Below is a graphical overview of Santos pulled from a June investor presentation.
This article was sent to 108 people who get email alerts on STOSF.
Get email alerts on STOSF »
(click to enlarge)
The PNG LNG project is a very positive catalyst for Santos. Bloomberg reported yesterday that Exxon Mobil (NYSE:XOM), the plant operator, said the plant is now operating at full capacity after initial startup earlier this year began ahead of schedule. Santos has a 13.5% equity stake in the 6.9 mtpa plant. ("mtpa" stands for million tonnes per annum). The plant has the majority of capacity (6.6 mtpa) contracted out to 2034 and is supplying companies like Tokyo Electric Power Co., CPC Corp. of Taiwan, Osaka Gas Co. and China Petroleum & Chemical Corp.
(click to enlarge)
PNG LNG joins Santos' Darwin LNG plant as the company's second producing LNG asset. Santos has an 11.5% equity stake in the Darwin LNG plant, which has a 3.7 mtpa plant capacity and which is fully contracted out to 2022.
The Queensland GLNG plant, in which Santos has a 30% equity stake and is the operator, has a 7.8 mtpa capacity and is currently under construction. Other partners include Total (NYSE:TOT) and Petronas, and KOGAS. The project is currently ~80% complete and Train 1 first LNG expected in 2015. Train 2 first LNG expected 6-9 months after Train 1 with LNG production expected to ramp-up to full capacity over 2-3 years. Each of the two trains is responsible for half (3.9 mtpa) of the total capacity. A photo of the GLNG plant, which is located on Curtis Island, is shown below:
(click to enlarge)
Two additional near-term growth opportunities are Darwin LNG and expansion of the PNG LNG operation.
All of these LNG plants are chasing after burgeoning natural gas demand from Asia (see below). Not only will the much publicized US LNG exports not be able to fully satisfy this Asian demand, but suppliers like Australian based Santos have a geographical advantage over its US competitors.
(click to enlarge)
Conventional Projects
In addition to its LNG efforts, Santos has numerous conventional assets as well. These include:
Peluang, Indonesia (Santos 67.5%): March startup came in on budget and ahead of schedule. Estimated production rate of 25 mmscf/d.
Dua, Vietnam (Santos 31.875%): First oil was achieved recently with an expected max production rate of 8,000 bbls/d.
The Browse and Cooper Basins, where Santos now has two shale wells now producing.
But it is the company's LNG projects that are transformational. The company has clear visibility on substantial growth in production and margins.
Financial Performance
While full-year production in 2013 was down 2% yoy, and the dividend remained unchanged at $0.15/share, highlights from the company's full-year 2013 financial results include:
Production of 51 million boe (-2%)
Revenue of $3.6 billion (+12%)
EBITDAX of $1.99 billion (+7%)
First 6 Months of 2014 Financial Results
On July 18th Santos announced Q2 and YTD results for the period ending June 30, 2014. The company announced a significant jump in revenue as a result of the successful early startup of PNG LNG:
Q2 production of 12.8 mmboe was an increase of 5% compared to the previous quarter and an increase of 3% compared to Q2 of 2013.
Sales revenue of $974 million for Q2 and $1,887 million for the first half increased by 22% and 25% respectively when compared to 2013.
Q2 yoy and sequential results are summarized below:
(click to enlarge)
Santos Managing Director and CEO David Knox commented on the results:
Delivery of the PNG LNG project is an important milestone for Santos in our journey to becoming a major LNG supplier to Asia. This project will significantly lift Santos' LNG production once the project reaches full output, and we are already seeing the contribution it is making.
Knox also said PNG LNG had already shipped 7 LNG cargoes by the end of Q2 and was building momentum for a stronger second half.
Operationally, the company reported the GLNG project had met key project milestones and was on track to meet first LNG in 2015. On the exploration front, the company reported its Barossa-2 appraisal well was successfully drilled and hit 92 meters of net gas pay. In addition, first oil was achieved from the Dua project in Vietnam (gross production to reach 8,000 bbls/day - 2,550 bpd net to Santos).
Impact of PNG LNG on Production Volumes
Santos' production profile from the Q2 EPS report:
(click to enlarge)
From the chart we can see that total gas energy production in the quarter, (gas+ethane)+LNG, was:
43.8 + 11.9 = 55.7 PJ (~9.6 million boe).
Gross gas production from PNG LNG for the quarter, as measured at the inlet to the LNG plant, was 50 PJ (Santos' share was 6.7 PJ). (PJ=petajoule). Gross condensate production for the quarter measured at the Kutubu entry point was 1.34 million bbls (Santos share was 180,500 barrels).
For the quarter, Santos' total share from PNG LNG was equivalent to ~14,700 boe/d. (NOTE: As an American, I needed to translate from PJ to boe/d to make sense of it all).
Exxon said it is currently loading the 15th cargo from PNG LNG. Since Santos CEO Knox said 7 cargoes had been shipped by the end of Q2 (June 30th), this means that roughly 8 cargoes will have been loaded in the month of July. This equates to an estimated 24 cargoes for the current quarter (Q3) assuming there are no interruptions and that cargoes are loaded at the July rate for the rest of the quarter. So, for Q3 we can expect Santos' share of production will be roughly 24/7 or ~3.4x the production of Q2:
6.7 x 3.4 = 22.8 PJ gas
180,500 x 3.4 = 613,700 bbls condensate
As an Exxon shareholder, the significant condensate production was a pleasant surprise to me - I was expecting only LNG. Regardless, 22.8 PJ gas equates to roughly 4 million boe. So let's call Santos' share of PNG LNG's estimated Q3 production (LNG+condensate) to be 4.6 mmboe (~51,110 boe/d). That equates to ~36% of Santos' total Q2 production (12.8 mmboe or ~142,220 boe/d). Obviously PNG LNG is going to have a very significant impact on Santos' production, revenue, and earnings going forward.
2014 Guidance
Santos says 2013 was the peak year in cap-ex spending and that cap-ex will drop to $3.5 billion in 2014, about $600 million less than last year's $4.1 billion.
The midpoint of the company's 2014 full-year production guidance is for 54.5 mmboe (~149,300 boe/d), up 6.9% yoy. From the chart above, we can see YTD production so far in 2014 is 25 mmboe. With the big increase expected in Q3 production as a result of PNG LNG's successful startup, it is surprising the company did not raise full-year production guidance in its Q2 EPS release. I think the company is being conservative. In the Bloomberg article cited earlier, Neil Beveridge, a Hong Kong-based oil and gas analyst at Sanford C. Bernstein & Co., said:
Having reached full capacity within three months of startup is exceptionally good performance by comparison with most international LNG projects.
As a result, Beveridge said he expects Oil Search Ltd., another partner in the PNG LNG project, to reach the high end of the its production forecast of 17 million to 20 million barrels of oil equivalent. While there are many moving parts to Santos' production profile (see chart above), the PNG LNG project has such an over-sized contribution that it is difficult to see, barring production interruptions at PNG LNG, how the company will not significantly beat its full-year 2014 guidance. After all, I have just shown how PNG LNG's contribution to Santos' overall production will almost triple from ~14,700 boe/d in Q2 to over 50,000 boe/d in Q3. And remember, the company's total production in Q2 was only 142,220 boe/d.
Remember too that Santos is the operator and has a 30% stake in the GLNG plant which is scheduled to come online next year. GLNG has a 7.8 mtpa capacity (13% larger than PNG LNG). So not only is Santos' equity stake in GLNG more than twice as large as its stake in PNG LNG, the total capacity of the plant is bigger as well. As a result, the company's investments in LNG are certainly going to be transformational. Assuming PNG LNG continues its successful operation, and GLNG is similarly successful, LNG will dominate Santos' production profile by 2016.
Valuation
(click to enlarge)
Santos Limited trades under the symbol STO on the Australian stock exchange and as STOFS on the US over-the-counter market. To the left, I have reproduced some share data from the Wall Street Journal's webpage on Santos' Australian shares.
A P/E ratio of 27 does not seem overly generous considering Santos' LNG prospects and the company's own guidance for operating cash flow to double by 2016. In addition, I noted earlier that 2013 was the peak year in cap-ex and that cap-ex will drop some $600 million from last year. So we have a very nice scenario here: cap-ex is falling while LNG production is rising.
The Dividend
A 10-year dividend summary from Santos's dividend webpage:
(click to enlarge)
Note Santos's dividend policy is for twice-a-year payments. Note also the company's dividend fell from $0.42/year in 2009 to the current $0.30/year. No doubt the dividend drop was a result of the worldwide financial crisis, lower oil and gas prices, and the company's decision to invest in very large LNG projects. But the tide has turned, and the company has said it is committed to increasing shareholder returns as the PNG LNG and GLNG projects come online. Well, PNG LNG is online, it is ahead of schedule, and it is performing beautifully. In addition, it helps Santos' risk profile to have a large and well respected operator like Exxon Mobil in charge of PNG LNG.
Risks
There are always risks associated with large LNG projects - just ask Chevron about its Angola LNG plant. However, it would appear Exxon has found the engineering "magic" and has done a great job of bringing the PNG LNG project online ahead of schedule. The fact that Exxon has already ramped out to full-production so soon after start-up is great news for Santos. Going forward, all eyes will be on Santos to repeat this success on the GLNG project next year. Working alongside Exxon on the PNG LNG project can only have been beneficial for Santos.
Note To US Investors
Santos is currently trading at $14.38 AUD in Australia and at $13.60 US on the OTC. Taking into account the foreign currency exchange (1 AUD = 0.94 USD), the stocks are trading in-line on the two exchanges. According to Yahoo finance, the company is very thinly traded on the US OTC market (~822 shares/day), yet many US investors will find it much easier to buy on the OTC. Due to the lack of liquidity on the OTC, investors should place limit orders only.
Summary & Conclusion
Santos Limited is transforming itself into a major player in the Asian LNG market. The company is riding the success of operator Exxon Mobil's early start and fast production ramp-up of the Papua New Guinea LNG plant. While Santos has a relatively small 13.5% stake in the plant, it is having a very large impact on the company's production profile. In addition, the company is on schedule (80% complete) on the even larger GLNG plant which is on-track to start-up next year. Not only is this plant larger than PNG LNG, but Santos has a much larger equity stake (30%). Capital expenditures are falling, production is rising, and the outlook for dividend growth is excellent. The company's own guidance is for cash flow to double by 2016. On the production front, my analysis of Santos' share of PNG LNG cargoes shows the company's production guidance (set at the beginning of the year) is quite conservative. While YTD revenue is up a very respectable +25%, Q3 is going to be an excellent quarter. It will be the first full quarter of PNG LNG production contributions. Investors should get in early. In 2013, the Q3 EPS report came out in mid-October. Santos could easily gain 40% by year-end on the back of Exxon's successful start-up of the PNG LNG plant. If Santos is as successful with its own operation of GLNG start-up next year, the stock could easily double by the end of 2015 because the company predicts a doubling of cash-flow. Santos Limited is a STRONG BUY.
Editor's Note: This article discusses one or more securities that do not trade on a major exchange. Please be aware of the risks associated with these stocks.
Additional disclosure: I am an engineer, not a CFA. The information and data presented in this article were obtained from company documents and/or sources believed to be reliable, but have not been independently verified. Therefore, the author cannot guarantee their accuracy. Please do your own research and contact a qualified investment advisor. I am not responsible for investment decisions you make. Thanks for reading and good luck! NOTE: The author may purchase shares of Santos Limited over the next 48 hours.
This article is part of Seeking Alpha PRO and is available to you on a time-limited basis. Fund managers subscribe to PRO to discover
research & experts on 4,000+ small & mid-cap stocks in the PRO library.
Learn More about PRO
View The Latest Top Ideas »
Share this article with a colleague
0
inShare
About this article
Operationally, the company reported the GLNG project had met key project milestones and was on track to meet first LNG in 2015. On the exploration front, the company reported its Barossa-2 appraisal well was successfully drilled and hit 92 meters of net gas pay. In addition, first oil was achieved from the Dua project in Vietnam (gross production to reach 8,000 bbls/day - 2,550 bpd net to Santos).
Impact of PNG LNG on Production Volumes
Santos' production profile from the Q2 EPS report:
(click to enlarge)
From the chart we can see that total gas energy production in the quarter, (gas+ethane)+LNG, was:
43.8 + 11.9 = 55.7 PJ (~9.6 million boe).
Gross gas production from PNG LNG for the quarter, as measured at the inlet to the LNG plant, was 50 PJ (Santos' share was 6.7 PJ). (PJ=petajoule). Gross condensate production for the quarter measured at the Kutubu entry point was 1.34 million bbls (Santos share was 180,500 barrels).
For the quarter, Santos' total share from PNG LNG was equivalent to ~14,700 boe/d. (NOTE: As an American, I needed to translate from PJ to boe/d to make sense of it all).
Exxon said it is currently loading the 15th cargo from PNG LNG. Since Santos CEO Knox said 7 cargoes had been shipped by the end of Q2 (June 30th), this means that roughly 8 cargoes will have been loaded in the month of July. This equates to an estimated 24 cargoes for the current quarter (Q3) assuming there are no interruptions and that cargoes are loaded at the July rate for the rest of the quarter. So, for Q3 we can expect Santos' share of production will be roughly 24/7 or ~3.4x the production of Q2:
6.7 x 3.4 = 22.8 PJ gas
180,500 x 3.4 = 613,700 bbls condensate
As an Exxon shareholder, the significant condensate production was a pleasant surprise to me - I was expecting only LNG. Regardless, 22.8 PJ gas equates to roughly 4 million boe. So let's call Santos' share of PNG LNG's estimated Q3 production (LNG+condensate) to be 4.6 mmboe (~51,110 boe/d). That equates to ~36% of Santos' total Q2 production (12.8 mmboe or ~142,220 boe/d). Obviously PNG LNG is going to have a very significant impact on Santos' production, revenue, and earnings going forward.
2014 Guidance
Santos says 2013 was the peak year in cap-ex spending and that cap-ex will drop to $3.5 billion in 2014, about $600 million less than last year's $4.1 billion.
The midpoint of the company's 2014 full-year production guidance is for 54.5 mmboe (~149,300 boe/d), up 6.9% yoy. From the chart above, we can see YTD production so far in 2014 is 25 mmboe. With the big increase expected in Q3 production as a result of PNG LNG's successful startup, it is surprising the company did not raise full-year production guidance in its Q2 EPS release. I think the company is being conservative. In the Bloomberg article cited earlier, Neil Beveridge, a Hong Kong-based oil and gas analyst at Sanford C. Bernstein & Co., said:
Having reached full capacity within three months of startup is exceptionally good performance by comparison with most international LNG projects.
As a result, Beveridge said he expects Oil Search Ltd., another partner in the PNG LNG project, to reach the high end of the its production forecast of 17 million to 20 million barrels of oil equivalent. While there are many moving parts to Santos' production profile (see chart above), the PNG LNG project has such an over-sized contribution that it is difficult to see, barring production interruptions at PNG LNG, how the company will not significantly beat its full-year 2014 guidance. After all, I have just shown how PNG LNG's contribution to Santos' overall production will almost triple from ~14,700 boe/d in Q2 to over 50,000 boe/d in Q3. And remember, the company's total production in Q2 was only 142,220 boe/d.
Remember too that Santos is the operator and has a 30% stake in the GLNG plant which is scheduled to come online next year. GLNG has a 7.8 mtpa capacity (13% larger than PNG LNG). So not only is Santos' equity stake in GLNG more than twice as large as its stake in PNG LNG, the total capacity of the plant is bigger as well. As a result, the company's investments in LNG are certainly going to be transformational. Assuming PNG LNG continues its successful operation, and GLNG is similarly successful, LNG will dominate Santos' production profile by 2016.
Valuation
(click to enlarge)
Santos Limited trades under the symbol STO on the Australian stock exchange and as STOFS on the US over-the-counter market. To the left, I have reproduced some share data from the Wall Street Journal's webpage on Santos' Australian shares.
A P/E ratio of 27 does not seem overly generous considering Santos' LNG prospects and the company's own guidance for operating cash flow to double by 2016. In addition, I noted earlier that 2013 was the peak year in cap-ex and that cap-ex will drop some $600 million from last year. So we have a very nice scenario here: cap-ex is falling while LNG production is rising.
The Dividend
A 10-year dividend summary from Santos's dividend webpage:
(click to enlarge)
Note Santos's dividend policy is for twice-a-year payments. Note also the company's dividend fell from $0.42/year in 2009 to the current $0.30/year. No doubt the dividend drop was a result of the worldwide financial crisis, lower oil and gas prices, and the company's decision to invest in very large LNG projects. But the tide has turned, and the company has said it is committed to increasing shareholder returns as the PNG LNG and GLNG projects come online. Well, PNG LNG is online, it is ahead of schedule, and it is performing beautifully. In addition, it helps Santos' risk profile to have a large and well respected operator like Exxon Mobil in charge of PNG LNG.
Risks
There are always risks associated with large LNG projects - just ask Chevron about its Angola LNG plant. However, it would appear Exxon has found the engineering "magic" and has done a great job of bringing the PNG LNG project online ahead of schedule. The fact that Exxon has already ramped out to full-production so soon after start-up is great news for Santos. Going forward, all eyes will be on Santos to repeat this success on the GLNG project next year. Working alongside Exxon on the PNG LNG project can only have been beneficial for Santos.
Note To US Investors
Santos is currently trading at $14.38 AUD in Australia and at $13.60 US on the OTC. Taking into account the foreign currency exchange (1 AUD = 0.94 USD), the stocks are trading in-line on the two exchanges. According to Yahoo finance, the company is very thinly traded on the US OTC market (~822 shares/day), yet many US investors will find it much easier to buy on the OTC. Due to the lack of liquidity on the OTC, investors should place limit orders only.
Summary & Conclusion
Santos Limited is transforming itself into a major player in the Asian LNG market. The company is riding the success of operator Exxon Mobil's early start and fast production ramp-up of the Papua New Guinea LNG plant. While Santos has a relatively small 13.5% stake in the plant, it is having a very large impact on the company's production profile. In addition, the company is on schedule (80% complete) on the even larger GLNG plant which is on-track to start-up next year. Not only is this plant larger than PNG LNG, but Santos has a much larger equity stake (30%). Capital expenditures are falling, production is rising, and the outlook for dividend growth is excellent. The company's own guidance is for cash flow to double by 2016. On the production front, my analysis of Santos' share of PNG LNG cargoes shows the company's production guidance (set at the beginning of the year) is quite conservative. While YTD revenue is up a very respectable +25%, Q3 is going to be an excellent quarter. It will be the first full quarter of PNG LNG production contributions. Investors should get in early. In 2013, the Q3 EPS report came out in mid-October. Santos could easily gain 40% by year-end on the back of Exxon's successful start-up of the PNG LNG plant. If Santos is as successful with its own operation of GLNG start-up next year, the stock could easily double by the end of 2015 because the company predicts a doubling of cash-flow. Santos Limited is a STRONG BUY.
Reply

#2
Thanks JFT, it does look like a very bright time for STO over the next year, but somehow a doubling of price by the end of 2015 may be a bit optimistic. Probably the increase in local Australian gas prices over this time period will also help STO profits, so maybe they are correct. We can only hope.
Reply

#3
I wanted to show what a 2 train LNG project does to others cash flow and how that's perceived by the analyst's
Reply

#4

[quote='jft310' pid='47953' dateline='1406808853']

Risks
There are always risks associated with large LNG projects - just ask Chevron about its Angola LNG plant. However, it would appear Exxon has found the engineering "magic" and has done a great job of bringing the PNG LNG project online ahead of schedule. The fact that Exxon has already ramped out to full-production so soon after start-up is great news for Santos. Going forward, all eyes will be on Santos to repeat this success on the GLNG project next year. Working alongside Exxon on the PNG LNG project can only have been beneficial for Santos.
Note To US Investors
Santos is currently trading at $14.38 AUD in Australia and at $13.60 US on the OTC. Taking into account the foreign currency exchange (1 AUD = 0.94 USD), the stocks are trading in-line on the two exchanges. According to Yahoo finance, the company is very thinly traded on the US OTC market (~822 shares/day), yet many US investors will find it much easier to buy on the OTC. Due to the lack of liquidity on the OTC, investors should place limit orders only. [quote]
Thanks JFT.  Got to admit this looks quite enticing after a quick scan.  Surprising to see so few shares traded on OTC given its prominence in Austrailia.  The lack of liquidity on OTC seems to make this a consideration only on the AX exchange.  Too much lliquidity risk here.  But I rarely have traded  on OTC.  Your comments?
Kaliboo

Reply

#5
Ask your broker dealer if they can place a trade on the Australian exchanges.