Per the MD&A for the 6 months ending June 30 the site prep, pre-spud and drilling costs for the 3 exploration wells were as follows:
Q2 YTD 6/30
$24.4 $36.4 Costs for site preparation, pre-spud work and drilling of the Raptor-1 well.
$19.2 $26.5 Costs for site preparation, pre-spud work and drilling of the Wahoo-1 well.
$24.3 $32.1 Costs for site preparation, pre-spud work and drilling of the Bobcat-1 well.
Nowhere near where someone was saying a while back.
Posts: 1,670
Threads: 49
Joined: Jan 2012
Reputation:
91
'Palm' pid='48460' datel Wrote:
Per the MD&A for the 6 months ending June 30 the site prep, pre-spud and drilling costs for the 3 exploration wells were as follows:
Q2 YTD 6/30
$24.4 $36.4 Costs for site preparation, pre-spud work and drilling of the Raptor-1 well.
$19.2 $26.5 Costs for site preparation, pre-spud work and drilling of the Wahoo-1 well.
$24.3 $32.1 Costs for site preparation, pre-spud work and drilling of the Bobcat-1 well.
Nowhere near where someone was saying a while back.
Palm - Thanks much for those numbers. Also,do you know if the new Zebra seismics are east of Elk or east of Antelope ? Appreciate your help.
Posts: 8,568
Threads: 1,342
Joined: Dec 2011
Reputation:
380
Antelope 4 per the new slides is south and east(right on slide ) of Ant 2. Ant 5 is further west and parallel to (left on slides)Ant 2.. They are testing the outer fringe of Antelope with these 2 wells.
Posts: 8,568
Threads: 1,342
Joined: Dec 2011
Reputation:
380
08-14-2014, 12:56 AM
(This post was last modified: 08-14-2014, 12:59 AM by jft310.)
The poster who talked to that "analyst" for drilling costs was not very analytic or accurate.Hint we have no rig rental for two of the rigs. I sincerely doubt if Morgan,Ray Jay or Macquarie provided those estimates of drilling costs. FWIW
Posts: 2,904
Threads: 58
Joined: Mar 2012
Reputation:
259
'Palm' pid='48460' dateline='<a href="tel:1407939 Wrote:
Per the MD&A for the 6 months ending June 30 the site prep, pre-spud and drilling costs for the 3 exploration wells were as follows:
Q2 YTD 6/30
$24.4 $36.4 Costs for site preparation, pre-spud work and drilling of the Raptor-1 well.
$19.2 $26.5 Costs for site preparation, pre-spud work and drilling of the Wahoo-1 well.
$24.3 $32.1 Costs for site preparation, pre-spud work and drilling of the Bobcat-1 well.
Nowhere near where someone was saying a while back.
Thx Palm. Hopefully those reporting those wild numbers will challenge their sources a little more diligently. I recall seeing $75 million per well and climbing a couple weeks back.
Posts: 2,623
Threads: 61
Joined: Dec 2011
Reputation:
225
I was pretty sure when they were speculating about and spouting those numbers that they did not know what they were talking about, and I think challenged them and got a lot of flack back. Hopefully, you're right, Art, and they learned something from that which will affect their attitudes and behavior.
Posts: 6,851
Threads: 697
Joined: Dec 2011
Reputation:
441
'sageo' pid='48464' datel Wrote:
'Palm' pid='48460' datel Wrote:
Per the MD&A for the 6 months ending June 30 the site prep, pre-spud and drilling costs for the 3 exploration wells were as follows:
Q2 YTD 6/30
$24.4 $36.4 Costs for site preparation, pre-spud work and drilling of the Raptor-1 well.
$19.2 $26.5 Costs for site preparation, pre-spud work and drilling of the Wahoo-1 well.
$24.3 $32.1 Costs for site preparation, pre-spud work and drilling of the Bobcat-1 well.
Nowhere near where someone was saying a while back.
Palm - Thanks much for those numbers. Also,do you know if the new Zebra seismics are east of Elk or east of Antelope ? Appreciate your help.
Sageo, I believe Zebra is SE of EA a ways. It's in PPL 476 which is east and then goes down to the SE of PRL 15 toward Wahoo.
Posts: 1,670
Threads: 49
Joined: Jan 2012
Reputation:
91
'Palm' pid='48478' datel Wrote:
'sageo' pid='48464' datel Wrote:
'Palm' pid='48460' datel Wrote:
Per the MD&A for the 6 months ending June 30 the site prep, pre-spud and drilling costs for the 3 exploration wells were as follows:
Q2 YTD 6/30
$24.4 $36.4 Costs for site preparation, pre-spud work and drilling of the Raptor-1 well.
$19.2 $26.5 Costs for site preparation, pre-spud work and drilling of the Wahoo-1 well.
$24.3 $32.1 Costs for site preparation, pre-spud work and drilling of the Bobcat-1 well.
Nowhere near where someone was saying a while back.
Palm - Thanks much for those numbers. Also,do you know if the new Zebra seismics are east of Elk or east of Antelope ? Appreciate your help.
Sageo, I believe Zebra is SE of EA a ways. It's in PPL 476 which is east and then goes down to the SE of PRL 15 toward Wahoo.
Palm - More thanks for your follow-up. I will try to find those seismic lines on another site. Very much interested in what they might reveal .
Posts: 6,851
Threads: 697
Joined: Dec 2011
Reputation:
441
'sageo' pid='48481' datel Wrote:
'Palm' pid='48478' datel Wrote:
'sageo' pid='48464' datel Wrote:
'Palm' pid='48460' datel Wrote:
Per the MD&A for the 6 months ending June 30 the site prep, pre-spud and drilling costs for the 3 exploration wells were as follows:
Q2 YTD 6/30
$24.4 $36.4 Costs for site preparation, pre-spud work and drilling of the Raptor-1 well.
$19.2 $26.5 Costs for site preparation, pre-spud work and drilling of the Wahoo-1 well.
$24.3 $32.1 Costs for site preparation, pre-spud work and drilling of the Bobcat-1 well.
Nowhere near where someone was saying a while back.
Palm - Thanks much for those numbers. Also,do you know if the new Zebra seismics are east of Elk or east of Antelope ? Appreciate your help.
Sageo, I believe Zebra is SE of EA a ways. It's in PPL 476 which is east and then goes down to the SE of PRL 15 toward Wahoo.
Palm - More thanks for your follow-up. I will try to find those seismic lines on another site. Very much interested in what they might reveal .
Back in 2010 they did this presentation and on slide 24 it shows the Zebra location
http://www.interoil.com/iocfiles/documents/investorrelations/presentationanddocuments/2010/2010-11-22_IOC_Exploration_Investor_Presentation.pdf
Posts: 8,568
Threads: 1,342
Joined: Dec 2011
Reputation:
380
Looks like its part of the Antelope trend , SE of Antelope on slide 24,as Palm states.
|