Yesterday a new operational milestone was reached.
Raptor is the third well in a row to have exceeded it's original advertised forecasted days of operation by 100%.
Here's the full well count.
Wahoo - suspended after 213% (128 days of operation) of orignal forecast of 60 days. It's now been suspended for 73 days and counting.
Bobcat - continuing operations at 227% (204 days of operation) of original forecast of 90 days. The 250% date will be 10/16/2014.
Raptor - continuing operations at 201% (181 days of operation) of original forecast of 90 days. The 250% date will be 11/08/2014.
Antelope 4 - continuing operations at 10% (9 days of operation) of original forecast of 90 days (I think).