Energy World speeds up Philippine LNG project to tackle power shortfall
MANILA Oct 28 (Reuters) - Australian-listed Energy World Corp Ltd said on Tuesday it would start generating 400 megawatts from its 650-MW gas-fired power plant project in the Philippines by early next year to help avert rolling brownouts on the main Luzon island.
The power plant is part of Energy World's $750 million to $800 million Pagbilao LNG import and storage hub project in Quezon Province in Luzon.
It will run on liquefied natural gas to be shipped from Energy World's Sengkang LNG field in Indonesia or bought from the spot market.
"They (the Philippines' Department of Energy) have asked us to go faster in bringing the units into commercial operations," Energy World Chief Executive Stewart W. G. Elliot told Reuters by telephone from his Hong Kong office.
The Philippines, one of Asia's fast-growing economies, faces a power shortfall that energy officials said could trigger up to three hours of rolling brownouts a day in Luzon from March to July next year, hurting the country's revitalised manufacturing sector and booming call centre industries.
Last week, the government said it would count on big businesses with diesel-fuelled power generators to avert brownouts, as it struggles to get authority from parliament to get involved in power generation.
Siemens-manufactured gas turbine and generator units that will help produce 400 MW have arrived at the Pagbilao site, Elliot said.
In an Oct. 23 filing to the Australia Stock Exchange, Energy World said it had been approached by Philippine energy officials to bring the units into commercial operation "as soon as we can and we are therefore working diligently to meet the request".
"Under the accelerated programme, we hope to have the first 200 MW unit ready for generating power into the Luzon grid by early next year ... and the second 200 MW unit to come online shortly thereafter," the filing said.
Elliot said Energy World planned to boost the Pagbilao plant's generating capacity by 250 MW before the end of 2015 or early 2016 and expand it further to as much as 1,950 MW in three to four years.
"We will sell to the WESM," he said, referring to the Philippines' wholesale electricity spot market.
Hong Kong-based Energy World has a 20-year lease on land in Quezon for its LNG hub, the first in the Philippines, which is expected to have initial capacity to ship in up to 3 million tonnes of LNG a year.