Goldman Sachs Global Energy Conference and LNG roadshow
http://www.interoil.com/iocfiles/documen...%20PPT.pdf
|
LNG FROM PNG
|
|
01-06-2016, 06:58 PM
(This post was last modified: 01-06-2016, 07:03 PM by Justin94360.)
Goldman Sachs Global Energy Conference and LNG roadshow http://www.interoil.com/iocfiles/documen...%20PPT.pdf
01-06-2016, 09:04 PM
Good post, thanks Justin
Slide 10 is revealing With LNG deliveries at $7.59 the project makes a 10 percent profit .The unlevered IRR Internal Rate of Return is 16 percent .The levered IRR with 70 percent debt is 20 percent . So what happens to these robust numbers as LNG prices recover ?? Numbers from Wood Mac . Aug 2015. Slide 11 shows the drop off of LNG Supply expected per Wood Mac just as Papua is supposed to start up . Slide 17 shows with GLJ's mid estimate of 9.9 T's Interoil collects $1.7 Billion plus $517 million at FID or $2.2 Billion by 2017end?? if GLJ high case is right 11.8 T's Interoil collects $2.480 Bilion plus $517 million at FID or $3 Billion by 2017 end?? How many think the resource estimate will not rise after this years drilling . ??
01-06-2016, 11:40 PM
When is the annual GLJ estimate due from IOC? Early March?
01-06-2016, 11:44 PM
Required by mid Feb for the 4th quarter report.45 days after the quarter ends. Most interesting to also see what Total and OIl Search estimate??
01-07-2016, 12:08 AM
Also note Zero mention of Ant 7....
01-07-2016, 08:02 PM
'jft310' pid='65732' datel Wrote:Also note Zero mention of Ant 7.... IOC is hinting at A7 in slide 14. I guess the extra resource is demonstrated with the red arrows on the westflank of the E/A field. Nevertheless, I can imagine that for a number of people the presentation is a disappointment. IOC is hiding itself behind the conservative projections of Wood Mackenzie dated August 2015.
01-07-2016, 10:46 PM
Appears the group of 3 has concluded they have enough gas for this first build . Why not tie into Oil Search appraisals and be done and collect the cash .
Relker any comments on your appeared use of 18 T's on your model ?!
01-08-2016, 05:50 AM
'jft310' pid='65758' datel Wrote:Appears the group of 3 has concluded they have enough gas for this first build . Why not tie into Oil Search appraisals and be done and collect the cash . Relker any comments on your appeared use of 18 T's on your model ?! Because: 1. Not iaw the contract. 2. There is the question of whether more information from the West side of the formation could be sufficiently useful for the project, which could also justify/require much more cash due under the contract, to be determined by IOC and Total.
01-08-2016, 05:59 AM
'jft310' pid='65729' datel Wrote:Required by mid Feb for the 4th quarter report.45 days after the quarter ends. Most interesting to also see what Total and OIl Search estimate?? The "4th quarter"/year end financial report and SEC filings are NOT due "45 days after the quarter ends", but rather 90 days after year end, by regulation. Is there a separate due date for the updated resource estimates from GLJ? They probably will be done sometime sooner in any case, but probably not because of such a 45-day SEC requirement. |
|